Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-01011 General Inspection5/17/20165/17/20165/18/2016 2:58:15 PM PASS
ESC15-01210 General Inspection5/17/20165/17/20165/17/2016 4:27:51 PMPPASS
WIP on road improvement leading up to the subdivision. No significant trackout or dust observed. No recent complaints. Should be done paving by end of the week and perimeter wattles and other temp BMPs will need to be installed. No corrections issued.
ESC16-00199 DOC - Permit Finaled5/17/20165/17/20165/17/2016 3:06:58 PMPPASS
Cinnabon station is installed. No ESC issues. All permits finaled.
ESC15-00391 General Inspection5/17/20165/17/20165/17/2016 2:29:53 PM PASS
ESC16-00023 BMP Violation5/17/20165/17/20165/17/2016 2:14:31 PMPCANC
disregard. SWO still active
ESC15-00893 General Inspection5/17/20165/17/20165/17/2016 2:11:01 PM PASS
WIP at North Pointe commercial. Access road is now paved, so no trackout outside of developement. Private storm drains onsite have sediment protection and they are trying to keep construction traffic off permeable pavers.

No discharges offsite, no fugitive dust issue. Saxton and State street are in decent condtion. Need to removal old boards in gutter that were used for a temporary ramp.
ESC15-01420 General Inspection5/17/20165/17/20165/17/2016 1:29:00 PMPPASS
Utilities and roadork in new subdivison development is complete. No SFH activity occuring yet. Vegetated swale installed south of sub has been hydroseeded and is being irrigated. No ESC violations at site.
ESC16-00341 General Inspection5/11/20165/17/20165/17/2016 1:23:15 PMPFAIL
Inadequate clean up of loose sediment trackout to street, gutter and sidewalk. Permit sign not visible.

Compliance due 5/18 AM
ESC16-00322 Stop Work Order5/17/20165/17/20165/17/2016 1:13:31 PMPPEND
No clean up of sidewalk and repair of wattles on two CBH homes on Hiawatha. Storm event was on Friday May 6, over 10 days ago. Corrections requested on Monday May 9 and also to Trilogy Development RP for Peppermill.

Corrections:
- sweep sidewalk and install wattles at 12010 Hiawatha
- sweep sidewalk and repair wattles on Heritage Street
- change out inlet bags on all storm drains in Peppermill sub.
- more sweeping and clean up needs to occur in dirty intersections and gutters.
- provide trash contaiment for this site and pick up windblown trash across street.

SWO issued for both homes. No inspections BLD or PLM until corrections have been completed
ESC16-00023 Stop Work Order5/17/20165/17/20165/17/2016 1:13:20 PMPPEND
No clean up of sidewalk and repair of wattles on two CBH homes on Hiawatha. Storm event was on Friday May 6, over 10 days ago. Corrections requested on Monday May 9 and also to Trilogy Development RP for Peppermill.

Corrections:
- sweep sidewalk and install wattles at 12010 Hiawatha
- sweep sidewalk and repair wattles on Heritage Street
- change out inlet bags on all storm drains in Peppermill sub.
- more sweeping and clean up needs to occur in dirty intersections and gutters.
- provide trash contaiment for this site and pick up windblown trash across street.

SWO issued for both homes. No inspections BLD or PLM until corrections have been completed
ESC15-01118 General Inspection5/17/20165/17/20165/17/2016 12:09:11 PM PASS
WIP. Flat industrial site with significant amount of permeable surface. No trackout, no discharges . Minimal activity occuring at time of inspection.
ESC15-01218 General Inspection5/17/20165/17/20165/17/2016 11:21:29 AM PASS
WIP at boat shop warehouse expansion. Project within large paved parking lot. No discharges or loose sediment leaving site. Foundation is poured and working on frame. No violations.
ESC15-00354 Aging Inspection5/17/20165/17/20165/17/2016 10:25:03 AM PASS
WIP on finish touches including final landscaping and clean up of street. No trackout, no discharges. Receiving storm drain has no sediment protection.
ESC15-00353 Aging Inspection5/17/20165/17/20165/17/2016 10:24:51 AM PASS
WIP on finish touches including final landscaping and clean up of street. No trackout, no discharges. Receiving storm drain has no sediment protection.
ESC15-00916 General Inspection5/17/20165/17/20165/17/2016 9:04:53 AM PASS
WIP on SFHs by Hayden HOmes. RP Tom Lane. DIs have sediment protection, designated washout provided, and permit signs posted.
ESC15-00995 Aging Inspection5/17/20165/17/20165/17/2016 8:39:52 AM PASS
No issues at site. No activity on BLD permit since September. Permit expired, no further ESC inspections
ESC15-00995 DOC - Permit Finaled5/17/20165/17/20165/17/2016 8:39:07 AMPPASS