ESC17-00416
| General Inspection | 5/18/2018 | 5/21/2018 | 5/24/2018 12:28:39 PM | P | PART |
|
|
Follow up:
- check for trash pick up around both homes - additional sediment catchment/perimeter control to be added in front of existing wattle.
DI bag on uphill side of Sand Dune was changed out. Trash around back mostly picked up, some items remain. No trackout or discharges.
Correction needed: - wattle/trench has faile and some sediment and sand has ran into downhill neighbors yard. Need to additional controls to slow and capture runoff between the two homes.
Correction request to Shane to fix and clean up this area. He stated that framers should be next week and will have excavator work on erosion issue. In meanwhile will take measures to prevent further sediment runoff to neighbor
|
ESC15-01579
| General Inspection | 5/21/2018 | 5/21/2018 | 5/24/2018 12:10:23 PM | | CANC |
|
|
rescheduled
|
ESC14-01083
| General Inspection | 5/21/2018 | 5/21/2018 | 5/23/2018 10:11:33 AM | P | PASS |
|
|
Trash behind stockpile west of site and in vegetated swale has been picked up. No new corrections requested
|
ESC17-00793
| BMP Violation | 5/15/2018 | 5/21/2018 | 5/23/2018 10:10:48 AM | P | PART |
|
|
follow up on wattle installation and clean up request
Street and sediment around inlets have been cleaned up. Additional rock bag check dams have been placed in gutter between site and storm drain. Perimter wattle re-installed and extended around trash box at driveway.
Correction not completed: - install slope interupting wattles on both slopes and runoff areas on either side of the home.
|
ESC16-00945
| Complaint Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 4:58:50 PM | P | PEND |
|
|
Silt fence along bottom of slope below common driveway was removed last week for landscaping. Site was left at risk and some sediment runoff occured to backyards below.
Landscaping on this slope and driveway paving is to be completed this week. Project manager ED with Perryman will Install sediment control wattle at bottom of slope in addtion to the rock line intercepting channel that will be below the landscaping.
Perryman is working with homeowner to repair damage to yard and remove any accumulated mud & sediment.
|
ESC17-01475
| Site Final | 5/21/2018 | 5/21/2018 | 5/21/2018 3:15:27 PM | P | PASS |
|
|
HOme complete and landscaped. No ESC corrections needed.
|
ESC17-01134
| Site Final | 5/21/2018 | 5/21/2018 | 5/21/2018 3:09:23 PM | P | PASS |
|
|
Home complete and landscaped. No corrections needed. All permits finaled.
|
ESC15-01288
| General Inspection | 5/18/2018 | 5/21/2018 | 5/21/2018 3:00:21 PM | P | PEND |
|
|
check on SFH drainage for projects on south side of Spotted Horse Dr.
Alturas homes is working on drainage channel behind homes on Spotted Horse and between older subdivsion homes (Glacier Street). Diversion/runoff channel has been increased in size.
Request to make sure dirt is not piled against fence. Need to stablize and line per construction details, clean up dirt deposited below unfinished section of channel. PW Hillside confirming drainage plans..
No corrections issued at this time. WIP. Alturas Construction is doing work, project manager Tim
|
ESC16-01650
| General Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 2:59:03 PM | | CANC |
|
|
|
ESC17-00446
| General Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 2:32:19 PM | | PASS |
|
|
|
ESC18-00754
| General Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 2:27:48 PM | P | PEND |
|
|
Soil test results received. Hauling contractor will begin stockpile removal tomorrow AM. Request to over excvate top layer and clean out soil placed in former basement depression.
Followed with DEQ Waste & Remediation on protocol for removal. DEQ inspector is also working with contractor.
|
ESC17-01662
| BMP Violation | 5/15/2018 | 5/21/2018 | 5/21/2018 12:32:44 PM | A | PASS |
|
|
Perimeter wattle repaired, construction entrance installed. Permit sign now posted. No new corrections.
|
ESC18-00128
| General Inspection | 5/18/2018 | 5/21/2018 | 5/21/2018 12:28:24 PM | P | PASS |
|
|
Perimeter wattles installed behind subdivsion fence and the wetland/vegetated area NE & behind homes on Rivernest. Some trash picked up. ESC permit sign posted on active ZEC site.
New project manager RP for ZEC homes here is Matt Sisco. 208.995.3394
Will discuss CGP coverage for being part of "common development"
|
ESC18-00177
| General Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 12:24:52 PM | P | PASS |
|
|
check on dewatering and creek opening..
WIP. Channel work occuring at south connection point @ Warm Springs bypass. Old channel has not yet been filled.
No discharges, trackout, or fugitive dust from site. Permits posted, construciton entrances installed.
|
MIS18-00186
| ESC-Conference | 5/18/2018 | 5/21/2018 | 5/21/2018 12:10:04 PM | P | PEND |
|
|
ESC permit obtained. Removal, clean up, and excavation of dumped soil, grading with clean fill and stabilization will be monitored under ESC18-00754
|
ESC17-00145
| Site Final | 5/2/2018 | 5/21/2018 | 5/21/2018 8:18:06 AM | A | DEFR |
|
|
project finaled 5/8 by BLD inspector
|
ESC17-00145
| DOC - Permit Finaled | 5/21/2018 | 5/21/2018 | 5/21/2018 8:17:49 AM | P | PASS |
|
|
|
ESC16-00812
| Aging Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 8:17:01 AM | | CANC |
|
|
|
ESC17-00141
| Site Final | 5/2/2018 | 5/21/2018 | 5/21/2018 8:03:05 AM | A | CANC |
|
|
|
ESC17-00141
| DOC - Permit Finaled | 5/21/2018 | 5/21/2018 | 5/21/2018 8:02:58 AM | P | PASS |
|
|
|