Inspections for the day of: Tuesday, May 22, 2018.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00836 General Inspection5/22/20185/22/20185/29/2018 8:07:02 AM CANC
ESC17-00392 General Inspection5/22/20185/22/20185/23/2018 4:07:00 PM FAIL
Muddy street, trackout not cleaned up. Works parking in the mud.

Stormwater swale north of building is not driaining. Need to check with owner and provide sediment protection in between swale and runoff from site.
ESC17-00807 Site Final5/22/20185/22/20185/23/2018 10:12:10 AMPPASS
Work complete. No disturbed area. Parking lot/staging area around building is paved/stabilized.
ESC18-00754 General Inspection5/21/20185/22/20185/22/2018 4:46:14 PMAPEND
Dirt stockpile removal in progress. Will request that top layer remaining after stockpiles are removed.
ESC16-00945 General Inspection5/22/20185/22/20185/22/2018 4:35:18 PMPCANC
rescheduled
ESC17-00824 General Inspection5/22/20185/22/20185/22/2018 4:34:30 PM CANC
ESC18-00190 BMP Violation5/21/20185/22/20185/22/2018 4:34:20 PMPFAIL
No new washout. Observed concrete truck driver use HHS washout container.

Final correction request to get a new washout by end of day tomorrow. Should be properly lined, marked with a sign, and have construction rock entrance to prevent trackout.
ESC17-00949 General Inspection5/22/20185/22/20185/22/2018 4:31:46 PMPPART
No trackout or discharges,

Correction request:

- install sediment protection on storm drain on Rim Street
- post ESC permit sign
ESC17-00808 General Inspection5/22/20185/22/20185/22/2018 12:59:22 PM CANC
ESC15-00857 General Inspection5/22/20185/22/20185/22/2018 12:59:01 PM CANC
ESC17-00807 General Inspection5/22/20185/22/20185/22/2018 12:50:54 PM CANC
ESC17-00455 General Inspection5/22/20185/22/20185/22/2018 8:22:51 AM CANC
ESC16-00989 General Inspection5/22/20185/22/20185/22/2018 8:22:23 AM PASS
revegetation in progress. Inspected 5/21 PM. No violations
ESC18-00190 BMP Violation5/18/20185/22/20185/21/2018 12:23:23 PMAPEND
concrete washout

RP stated the AM new washout has been ordered and will be installed. No trackout or use of full washout occuring.

Compliance extension to 5/22 PM
ESC18-00177 General Inspection5/8/20185/22/20185/21/2018 12:21:37 PMAPASS
Channel realignment is in process of being opened up. Knife River working on project. Lining connection areas with geotextile and rip rap. Groundwater in channel is being pumped to the adjacent pasture to the west. No turbid discharges in construction areas. Knife River active on grading & fill for DHETH 6-7 and DHE #17 and 404 permits to fill in old channel have been approved and will occur this week and next.

When channel by Warm Springs bybass is opened, plan is to capture sediment laden water from first flush in basin south of road and north of Greenbelt and discharge w/ 2 " pump to the vegetated area west of the creek. Will follow up.