Inspections for the day of: Wednesday, May 25, 2016.
Number of inspections: 28
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-01169 Aging Inspection5/25/20165/25/20165/26/2016 3:31:18 PM PASS
WIP. Trench stockpile stored on vegetated lawn with no runoff potential. NO trackout or materials leavings site
ESC16-00560 BMP Violation5/25/20165/25/20165/26/2016 3:12:15 PMPPART
Need to continue sweep up of cement residue in gutter. Use dust pan and collect in 10 gallon bucket.

Dirty site next to this project also issued corrections.
ESC14-00432 General Inspection5/25/20165/25/20165/26/2016 2:51:17 PM PASS
WIP on SFHs in Aralar all by Hayden Homes. Inlets bags installed to capture sediment, will need mainteance request next inspection if not cleaned already. Most approaching 50% capacity.

No trackout or discharges out of sub. No trash along creek bank. Roads relatively clean, and individual homes have permit signs as requested.

No corrections issued at this time.
ESC15-01158 Aging Inspection5/25/20165/25/20165/25/2016 4:37:06 PM PASS
Accesory dwelling in backyard at end of driveway is near completion. Permit sign posted, no discharges or sediment leaving site. Approved.
ESC16-00405 Site Preparation5/25/20165/25/20165/25/2016 3:51:11 PMPPASS
Follow up inspection -

Construction entrance installed with heavy rock and geotextile lining. Permit sign postedl Stockpile has been tacified.

Approved.
ESC15-01285 Site Final5/24/20165/25/20165/25/2016 3:39:35 PMAPASS
New path complete and open to public. Old path area has revegetated and site is stable. No DI bags remaining on MS4 inlet on Pioneer. ESC permit satisfied.
ESC15-00934 DOC - Permit Finaled5/25/20165/25/20165/25/2016 3:32:42 PMPPASS
ESC15-00934 General Inspection5/25/20165/25/20165/25/2016 3:32:35 PM PASS
Project construction complete. Materials removed. Murale painting crew finalizing exterior. DI bags removed, parking lot now to cleaned by property management stormwater O&M. ESC conditions satisfied.
ESC15-01373 Aging Inspection5/25/20165/25/20165/25/2016 3:10:53 PM PASS
Home demolished and lot is vegetated with weeds grasses and bushes. No activity. No sediment leaving site.
ESC15-01373 DOC - Permit Finaled5/25/20165/25/20165/25/2016 3:08:24 PMPPASS
ESC15-01268 General Inspection5/25/20165/25/20165/25/2016 2:57:17 PM PASS
Work complete, all permits finaled. No disturbed area or loose sediment/materials leaving site. No construction activity or staging.
ESC15-01268 DOC - Permit Finaled5/25/20165/25/20165/25/2016 2:56:00 PMPPASS
ESC15-00938 General Inspection5/25/20165/25/20165/25/2016 1:27:42 PMPPASS
WIP on cell tower and outbuilding. No trackout or sediment leaving site. No violations observed. Should be done in June.
ESC16-00132 DOC - Permit Finaled5/25/20165/25/20165/25/2016 1:18:48 PMPPASS
Pool covered seperately is complete and surrounding area stabilzed. No further ESC inspections.
ESC14-01011 Site Final5/25/20165/25/20165/25/2016 1:16:17 PMPPASS
Home complete and landscaped. Temporary BMP DI bags down hill on Castello were removed as requested. ESC permit finaled.
ESC15-01628 Random Inspection5/25/20165/25/20165/25/2016 12:14:17 PMPPASS
WIP. Near completion. Driveway poured so no trackout, yard below grade so low runoff potential from the yard that is not yet landscaped.
ESC03-00508 DOC - Permit Finaled5/25/20165/25/20165/25/2016 12:09:03 PMPPASS
old permit removed from database. no inspection
ESC15-01224 General Inspection5/25/20165/25/20165/25/2016 11:55:09 AMPPASS
WIP at library. Site perimeter is in good condition and no sediment runoff or issues observed. Construction entrance with rumble bars is installed. No violations. Clean site.
ESC15-00403 General Inspection5/25/20165/25/20165/25/2016 11:53:45 AM PASS
WIP. No trackout or discharges. Vegetated swale at corner of Bown and Parkcenter is undisturbed and berm keeps out sediment during rain. Construction fencing defines site limits. No corrections issued.
ESC15-01265 DOC - Permit Finaled5/25/20165/25/20165/25/2016 11:27:00 AMPPASS
ESC14-00788 General Inspection5/25/20165/25/20165/25/2016 11:26:53 AMPPASS
No SFH activity. Site is fully landscaped along Warm Spring. Upper drainage swale sides that had erosion are now re-raked and vegetated with grasses. No loose sediment or materials on impervious surface. No significant erosion rills on hillsides.

Approved.
ESC15-01265 DOC - Permit Finaled5/25/20165/25/20165/25/2016 11:22:17 AMPPASS
ESC14-00886 General Inspection5/25/20165/25/20165/25/2016 11:21:52 AM PASS
ESC15-00581 Aging Inspection5/25/20165/25/20165/25/2016 10:53:13 AM PASS
WIP. Minor activity, no trackout or loose sediment on pavement work area.
ESC16-00618 Site Preparation5/25/20165/25/20165/25/2016 10:28:42 AMAPASS
note: send RP class schedule

Permit sign posted. Closed out demo permit.

Backfill currently being hauled offsite to prevent sediment runoff. Wide flat sidewalk along Crescent Rim should prevent runoff but may require wattles if an issue.

Requested that sidewalk be swept today. DI is over 200 M west on Crescent Rim, no bag requested.
ESC16-00633 DOC - Permit Finaled5/25/20165/25/20165/25/2016 8:56:39 AMPPASS
Previous home and vegetation demolished and cleared. New SFH now under way. This permit finaled for AAI, permit for Gordon Beck is ESC16-00618.
ESC15-01266 General Inspection5/25/20165/25/20165/25/2016 8:15:36 AM PASS
Podium phase of project near completion. Vertical construction in progress. No violations at site.

ESC inspections of this project to be conducted under main site permit, ESC15-01175
ESC15-01266 DOC - Permit Finaled5/25/20165/25/20165/25/2016 8:14:19 AMPPASS