PDS Online
Making
Boise
the most livable city in the country.
Home
Permits
Search by Permit Number
How to search by permit number
Search by Address
Search by Customer Number
Search by Current Planning Number
Search in Project by Permit Number
Search by Project Name
Inspections
Search by Permit Number
Search by Request Date
Search by Company Name
Fees
Impact Fees Estimate Calculator
Other Searches
Search for Licensed Contractors
Search Parcel by Address
Search Historical Surveys
Reports
Daily Reports
Weekly Reports
Monthly Reports
Home
/
Inspections
/
Inspector Activity
Inspections for the day of:
Tuesday, May 8, 2018
.
Number of inspections:
13
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Andy J. Long
Title
EROSION INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC13-00193
General Inspection
5/8/2018
5/8/2018
5/10/2018 3:51:02 PM
CANC
ESC16-00625
General Inspection
5/8/2018
5/8/2018
5/9/2018 3:07:07 PM
PASS
ESC17-00711
General Inspection
5/8/2018
5/8/2018
5/9/2018 3:03:33 PM
PASS
ESC16-01561
Complaint Inspection
5/8/2018
5/8/2018
5/8/2018 4:51:03 PM
P
FAIL
Corrections needed. Notice issued to RP Zach with Brighton Corp and Braxton with Brighton Homes.
- pick up trash along Walling Creek. Enact daily or other day trash collection around perimeter, in particular along the wetland area.
- provide additional trash box for next set of units on Exacta
- post new SWPPP signage in clear and visible spot next to project
ESC18-00488
General Inspection
5/8/2018
5/8/2018
5/8/2018 4:46:01 PM
P
PART
Need to clean up trackout on Timbersaw. follow up inspection scheduled...
ESC18-00127
Complaint Inspection
5/8/2018
5/8/2018
5/8/2018 4:45:12 PM
P
FAIL
- pick up trash along Walling Creek path and in vegetation.
- add another trash box on Exacta
- remove straw wattles temporarily when the forklift needs to be used in these areas and re-install or replace when complete.
RP stated that trash pick up will be condcuted today.
ESC18-00177
Site Preparation
5/8/2018
5/8/2018
5/8/2018 4:43:23 PM
P
PASS
pre-con meeting DHE townhomes # 7
Knife River is contractor (Rex ###-####), Riverridge engineering project design.
construction entrance on east end of project. Will protect Warm Springs creek channel with silt fence until 404 permit approval to fill the channel as planned.
Standard BMPs required: dust control, trackout prevention and sweeping, concrete washout facility, staging area with safe storage or materials and chemicals on site.
Requested that silt fence crew also pick up loose trash encountered in the area.
ESC18-00133
Site Preparation
5/8/2018
5/8/2018
5/8/2018 3:57:33 PM
P
PASS
This project is located behind the Mormon temple on Cole. Call me if you have any questions. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
ESC17-00734
General Inspection
5/8/2018
5/8/2018
5/8/2018 2:07:57 PM
CANC
ESC16-00406
General Inspection
5/8/2018
5/8/2018
5/8/2018 2:07:49 PM
CANC
ESC17-00984
Aging Inspection
5/8/2018
5/8/2018
5/8/2018 10:14:15 AM
PASS
WIP on ADU in backyard. No ESC corrections needed at site. No sediment runoff or uncontained materials.
ESC14-01063
General Inspection
5/8/2018
5/8/2018
5/8/2018 7:59:46 AM
PASS
Inspected 5/7 PM. 2 SFHs in progress on Goshawk. Subdivision BMPs installed. No violations observed.
ESC17-01754
General Inspection
4/26/2018
5/8/2018
5/7/2018 11:45:12 AM
A
PASS
No activity at site. No trackout or dust issues observed.
Stockpile of dirt on the southeast end of site will need stabilization if inactive during next inspeciton.