Inspections for the day of: Thursday, June 1, 2017.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01269 Aging Inspection6/1/20176/1/20176/2/2017 3:27:03 PM PASS
ESC16-00208 General Inspection6/1/20176/1/20176/2/2017 3:22:46 PM CANC
ESC16-00849 General Inspection6/1/20176/1/20176/2/2017 3:15:57 PM PASS
WIP on interior wiriing. Permit sign posted, gutter is clean. Rear hillside retaining walls are installed. Some rill erosion on the SE slope will need work before landscaping. No sediment overtoping the perimeter BMPs. Another silt is at the low property line and will need removal upon completion. Native veegetation below main yard has been preserved. No corrections at this time.
ESC15-01210 General Inspection6/1/20176/1/20176/2/2017 3:02:08 PM PASS
WIP on SFHs that permitted seperately. No sediment runoff from open lots. Perimeter controls and storm drain inlet protection is installed.
ESC17-00351 Site Preparation6/1/20176/1/20176/2/2017 1:47:41 PMPPASS
Clint Phone #: ###-####

Subdivision BMPs installed. Approved for construction.
ESC17-00350 Site Preparation6/1/20176/1/20176/2/2017 12:39:35 PMPPASS
Clint Phone #: ###-####

Subdivision BMPs installed. Approved for construction
ESC16-00225 General Inspection6/1/20176/1/20176/2/2017 11:25:09 AM PEND
No new subdivision activity. All upper roads, sidewalks and gutters are free of loose dirt and sediment. Disturbed areas have revegetated well.

Corrections still in progress:
- increase sediment control on long gentle slope above Trent Point. Will also request Suez Water to complete access road to water tank and adjacent area
- need to address erosion rills above the east stormwater pond and below the stockpile. Stockpile has started to vegetate with volunteer plants but needs perimeter sediment control on downslope side.

ESC16-00853 General Inspection6/1/20176/1/20176/2/2017 11:17:02 AM PASS
Trackout from adjacent lot has been swept. RP on site. Trash has been removed and RP sweeping sidewalks/gutter. Requested that accumulated dirt in front of DI mat be cleaned.

The washout dumped next door will also be cleaned up per RP-GC Justin. No discharges or fugitive dust issues. No new corrections.
ESC16-00713 General Inspection6/1/20176/1/20176/2/2017 10:57:05 AM PASS
Home complete, occupied, stabilized/landscaped. BLD permit finaled with geotech approval. No ESC corrections or requests. Permit finaled.
ESC14-00657 General Inspection6/1/20176/1/20176/1/2017 8:00:17 AM PEND
All parcels within RH#6 are near completion. Still need to remove all temporary DI bags in storm drains through out subdivsion to get Site Final.