Inspections for the day of: Monday, June 11, 2018.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01232 General Inspection6/11/20186/11/20186/13/2018 12:09:58 PM PASS
No activity. Slopes on lot are mostly vegetated with grass and weeds.Silt fence installed at bottom of lot is trenched in with no breaks. No sediment runoff or hillside erosion on lot.
ESC17-00027 General Inspection6/11/20186/11/20186/11/2018 3:39:36 PM FAIL
Temporary BMPs left on site (DI bags, silt fence)
ESC18-00498 Conference6/11/20186/11/20186/11/2018 3:21:03 PMPDONE
pre-construction conference, City Hall 2 PM

Review ESC conditions with GRD permit conditions. Request for initial site preparation insepction to be completed and an inspection scheduled prior to earthwork beginning on Monday June 18th.
ESC17-00072 Aging Inspection6/11/20186/11/20186/11/2018 12:40:42 PM CANC
ESC17-01379 Site Final6/11/20186/11/20186/11/2018 12:27:09 PMPPASS
see ESC17-00657. No ESC corrections needed. Exteriour stabilized and cleaned, no temp. BMPs left on site.
ESC17-01380 Site Final6/11/20186/11/20186/11/2018 12:26:57 PMPPASS
see ESC17-00657. No ESC corrections needed. Exteriour stabilized and cleaned, no temp. BMPs left on site.
ESC17-00657 Site Final6/11/20186/11/20186/11/2018 12:18:04 PMPPASS
Grading, utility installation and paving of parking & operations lot is now complete. No loose dirt or construction materials left onsite. Silt fence on south end has been removed and sodded grass is growing well. No temporary BMPs left on site. ESC permit conditions satisfied.
ESC17-01731 General Inspection6/11/20186/11/20186/11/2018 11:26:52 AMAPASS
WIP on foundation. Permit sign posted. No trackout or fugitive dust observed. Large stockpile onsite. Will check back in two weeks for stabilizatio/dust control.
ESC17-00452 General Inspection6/11/20186/11/20186/11/2018 11:26:41 AMPPASS
ESC18-00123 Conference6/11/20186/11/20186/11/2018 9:59:33 AMPCANC
ESC16-01205 General Inspection6/11/20186/11/20186/11/2018 9:20:18 AM PASS
ESC16-00945 General Inspection6/11/20186/11/20186/11/2018 8:13:07 AM PASS
Inspection Friday 6/8 PM.

WIP on shoulder and sidewalk at the access drive. Access drive is paved and storm drain system hooked up. Landscaping the bank between retaining wall and fence of existing homes below.

They are still using bark and shrubberies, not grasses as Public Works had ordered. There is a sediment control wattle along the toe of the slope at the fence as well as some drain rock in several areas.

No erosion or runoff issues observed.
ESC39-00001 Aging Inspection6/11/20186/11/20186/11/2018 8:01:48 AM CANC
ESC17-00063 General Inspection6/11/20186/11/20186/11/2018 8:01:35 AM CANC
ESC17-00271 Aging Inspection6/11/20186/11/20186/11/2018 8:01:05 AM CANC
rescheduled for site final