ESC15-01196 General Inspection6/15/20166/15/20166/16/2016 12:45:29 PM PASS
Site is now adequately vegetated.

Spoke with Shane @ Cutting Edge. This week or next he will have temp BMPs removed:
- wattles around culdesac and upper storm drain
- remove 3 x sediment filters from DIs
- take down ESC permit sign

Shane stated he would call once this was complete for a site final.
ESC15-00453 General Inspection6/15/20166/15/20166/16/2016 12:27:46 PM PASS
Finishing touches in progress. Back slope and recently installed drainage swale have been hydroseeded and sediment control wattles have been installed. No trackout, no sediiment leaving site. Approved.
ESC15-01345 General Inspection6/9/20166/15/20166/16/2016 9:57:58 AMAPASS
ESC15-01410 Aging Inspection6/15/20166/15/20166/15/2016 3:06:18 PM PASS
Work complete. All permits finaled. No ESC issues.
ESC15-01410 DOC - Permit Finaled6/15/20166/15/20166/15/2016 3:06:02 PMPPASS
ESC15-01244 Aging Inspection6/15/20166/15/20166/15/2016 3:05:34 PM PASS
ESC15-00019 General Inspection6/15/20166/15/20166/15/2016 2:03:24 PM PASS
WIP. Final landscaping and park feature installation & clean up occuring.
ESC14-01083 General Inspection6/15/20166/15/20166/15/2016 1:18:55 PM PASS
WIP on townhomes. New phase roads now paved. No fugitive dust, trash or material wrappings, or non-stormwater discharges leaving site. No corrections issued at this time.
ESC16-00120 Site Preparation6/14/20166/15/20166/15/2016 11:57:32 AMAPASS
Clint Phone #: ###-####

Subdivsion BMPs installed. Active projecs in compliance. Approved for construction
ESC16-00439 Random Inspection6/15/20166/15/20166/15/2016 11:56:48 AMPPASS
No activity. BMPs installed, Water truck on site for when site is back in action. Will need some temporary or permanent stabilization once roads and infrastructure are installed. High wind area.
ESC15-01149 Aging Inspection6/15/20166/15/20166/15/2016 11:52:03 AM PASS
Home complete and landscaped. ESC conditions satisfied with exception of temp BMPs to remain while Sunnyridge 2 SFHs in progress.
ESC15-01149 DOC - Permit Finaled6/15/20166/15/20166/15/2016 11:51:52 AMPPASS
ESC15-01550 DOC - Permit Finaled6/15/20166/15/20166/15/2016 11:51:39 AMPPASS
Home complete and landscaped. ESC conditions satisfied with exception of temp BMPs to remain while Sunnyridge 2 SFHs in progress.
ESC15-01545 DOC - Permit Finaled6/15/20166/15/20166/15/2016 11:50:34 AMPPASS
Home complete and landscaped. ESC conditions satisfied with exception of temp BMPs to remain while Sunnyridge 2 SFHs in progress.
ESC15-01150 Aging Inspection6/15/20166/15/20166/15/2016 11:30:34 AM PASS
WIP on foundation. No corrections at this time.
ESC15-00221 General Inspection6/15/20166/15/20166/15/2016 11:24:13 AM PART
WIP on interior and backyard landscaping. Old driveway was recently removed so now there is signiifcant trackout and loose dirt & gravel in front of the home.

Verbal correction request issued to RP/GC Gordon to have street manually broom swept today. He stated it would be done.
ESC16-00492 General Inspection6/15/20166/15/20166/15/2016 10:27:05 AMAPASS
WIP. This permit to cover new BLD permit be issued as well. Same GC-RP. No violations or corrections needed at site.
ESC04-00623 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:55 AMPPASS
old permit still open in database removed. No inspection
ESC03-01643 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:46 AMPPASS
old permit still open in database removed. No inspection
ESC04-01421 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:38 AMPPASS
old permit still open in database removed. No inspection
ESC04-01060 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:31 AMPPASS
old permit still open in database removed. No inspection
ESC04-00505 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:23 AMPPASS
old permit still open in database removed. No inspection
ESC03-01231 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:15 AMPPASS
old permit still open in database removed. No inspection
ESC04-00647 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:24:07 AMPPASS
old permit still open in database removed. No inspection
ESC04-00220 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:23:59 AMPPASS
old permit still open in database removed. No inspection
ESC03-00647 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:23:46 AMPPASS
old permit still open in database removed. No inspection
ESC03-01167 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:23:37 AMPPASS
old permit still open in database removed. No inspection
ESC15-01237 Aging Inspection6/15/20166/15/20166/15/2016 10:19:32 AM PASS
Home complete. Yard landscaped and stabilized. No ESC issues, all permits finaled.
ESC15-01237 DOC - Permit Finaled6/15/20166/15/20166/15/2016 10:19:01 AMPPASS
ESC15-00853 General Inspection6/15/20166/15/20166/15/2016 10:10:04 AM PART
WIP on installing subsurface stormwater infrastructure. Site is clean with trash/debris consolidated for removal, no trackout, and no non-stormwater discharges.


Corrections needed:
- need to re-organize inspection reports in chronological order and make sure frequency matches that pre-scribed in the SWPPP.
ESC15-01210 Conference6/14/20166/15/20166/15/2016 9:42:53 AMAPASS
8:30 on-site meeting to discuss slope and hillside stabilization and other corrections.

Plan of action discussed with RP Pat and Syman Company Adam with Knife River foreman.

- paving of roads is to occur next week. Road base and curb and gutter has been installed.

- Sediment filter bags have been installed on the SH system inlets.

- Two gravel bag check dams shall be installed at bottom of sub to capture sediment/sand from site in stormwater that is flowing down old Sherman to Ada
- There is some movement of existing stockpiles that will also occur this week and next. Requested that dust levels be monitored and water truck be onsite.

- after paving and re-distribution of stockpiles (to be done this week and next), slope interuption/sediment control wattles will be installed on hillsides. For erosion control, a "tacifier with minimal mulch" will be used for stabilization until Sept-Oct when hydroseeding application

Corrections completed or in-progress:
- unused wattles have been collected to a single stockpile and will be removed by Syman
- gutter at Ada and Sherman was swept
- trash pile at top of site will be hauled off this week. and has now been consolidated
- DI bags along Ada Street have been maintained
ESC15-01307 General Inspection6/15/20166/15/20166/15/2016 9:29:07 AM PASS
WIP on frame. Somerset Village BMPs installed. No trackout or discharges occuring. No loose trash or debris. Approved.
ESC15-01308 General Inspection6/15/20166/15/20166/15/2016 9:28:52 AM PASS
WIP on frame. Somerset Village BMPs installed. No trackout or discharges occuring. No loose trash or debris. Approved.
ESC15-01437 General Inspection6/10/20166/15/20166/14/2016 12:20:21 PMAPART
Need to change out DI bag. Request also issued to landscaping/retaining wall project under ESC16-00269