Inspections for the day of: Thursday, June 16, 2016.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00684 General Inspection6/16/20166/16/20166/16/2016 4:44:39 PM PASS
ESC14-00657 General Inspection6/16/20166/16/20166/16/2016 4:35:37 PM PART
RH#6 is mostly good condition. No trackout, fugitive dust, or discharges obsered. DIs have filter bags and trash is being contained.

Corrections needed:

-Check DI bags for maintenance, observed some full bags.
- Pick up wind blown trash on south side of Warm Springs from building sites.
ESC15-01288 General Inspection6/16/20166/16/20166/16/2016 4:28:20 PM PASS
No trackout, no fugitive dust, no corrections at this time.
ESC16-00714 DOC - Permit Finaled6/16/20166/16/20166/16/2016 4:26:53 PMPPASS
Home complete, landscaped, and occupied. Permit conditions satisfied.
ESC15-01385 DOC - Permit Finaled6/16/20166/16/20166/16/2016 4:25:19 PMPPASS
Home complete, landscaped and stabilized. Temp BMPs in RH#6 to remain installed while rest of homes are completed.
ESC15-01341 Aging Inspection6/16/20166/16/20166/16/2016 4:13:56 PM PASS
ESC15-00745 Tracking Control6/16/20166/16/20166/16/2016 4:00:43 PMPPASS
Track out that was reported has been cleaned up. Rock construction entrance installed. Will need to stay vigilant but clean up has taken place in a timely manner.
ESC16-00384 Tracking Control6/16/20166/16/20166/16/2016 3:36:01 PMPFAIL
Track out from site to Victory. No construction entrance or trackout prevention BMP. No active cleanup.

Called RP with verbal correction notice.
ESC15-01499 Aging Inspection6/16/20166/16/20166/16/2016 1:01:55 PM PASS
Work complete. No materials or loose sediment/disturbed area on site. All permits finaled.
ESC15-01499 DOC - Permit Finaled6/16/20166/16/20166/16/2016 1:00:46 PMPPASS
ESC15-01340 General Inspection6/16/20166/16/20166/16/2016 12:53:59 PM PASS
BLD is open, but elevated deck with sun shade is constructed. No disturbed area around site or on the hillside below. Vegetation was preserved. ESC permit conditions satisfied.
ESC15-01340 DOC - Permit Finaled6/16/20166/16/20166/16/2016 12:52:34 PMPPASS
ESC16-00378 DOC - Permit Finaled6/16/20166/16/20166/16/2016 12:51:51 PMPPASS
All permits final. No further construction. Site is clean.
ESC15-01293 Site Final6/16/20166/16/20166/16/2016 12:10:29 PMPPASS
Building is complete. WIP by individual tennants with seperate ESC permits.

No further ESC inspections, North Pointe retail corrections listed under ESC15-00893
ESC15-00894 Site Final6/16/20166/16/20166/16/2016 12:10:01 PMPPASS
Building is complete. WIP by individual tennants with seperate ESC permits.

No further ESC inspections, North Pointe retail corrections listed under ESC15-00893
ESC15-00893 General Inspection6/16/20166/16/20166/16/2016 12:08:07 PM PEND
North Pointe #3 is complete. Final staging area clean up is needed to final ESC.

Request to Radix to clean up around the stormwater swale at Saxton and State. Remove silt fence, wind blown litter and debris. Onsite supervisor for Radix stated

NP # 1 ESC15-01292 open
NP # 2 ESC15-00894 closed out
NP # 3 (this permit, open for corrections listed above)
NP # 4 ESC15-01293 closed out
ESC15-00504 General Inspection6/15/20166/16/20166/16/2016 11:07:28 AMPPASS
Site walk through with RP-GC Barry with Bach Homes.

No trackout or discharges offsite, large designated lined washout containment is provided and approximately 50% full. Heavy duty construction entrance to Gary with lava rock is still in good condition. Perimeter silt fence on north property line is in place. No complaints or issues from neighbors directed to ESC division.

The road base of sand is prepped for asphalt, and pervious pavers are already installed and are off limits for driving and staging.

Correction request to have crew walk site and clean up loose trash, consolidate and contain/remove from site.. Barry said it would be done this week.

Approved.
ESC16-00627 Site Preparation6/16/20166/16/20166/16/2016 9:09:43 AMAPASS
Yellow card on site Inspection requested via web by Erby Gonzales

Subdivision BMPs installed. RH#6 Brighton Homes in compliance. Approved for construction
ESC15-01385 Aging Inspection6/16/20166/16/20166/16/2016 8:41:20 AM PASS