ESC14-01105
| General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 3:58:12 PM | | PASS |
|
|
St,. Lukes project is in progress. No trackout from entrance onto Idaho. Materials stored and contained properly. Approved.
|
ESC15-00023
| BMP Violation | 6/18/2015 | 6/19/2015 | 6/19/2015 3:20:02 PM | A | PASS |
|
|
Violations observed during inspection rounds; No BMPs, no permit posted, dirt in gutter and on top of DI
Correction issued to new RP/GC Rustin ###-####.
Corrections issued: 1. Post ESC permit sign in visible spot 2. Install BMPs per ESC plan 3. Clean sidewalk, gutter, and empty out DI bag
Will reinspect next week for corrections.
|
ESC14-00266
| General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 3:09:55 PM | | PEND |
|
|
Surrounding hillside areas disturbed during construction in process of revegetating. No hillside bond opened yet. BLD open. No ESC corrections at this time.
|
ESC14-00572
| General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 3:08:28 PM | | PASS |
|
|
|
ESC13-00117
| Aging Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 2:01:55 PM | | CANC |
|
|
|
ESC14-00529
| General Inspection | 6/18/2015 | 6/19/2015 | 6/19/2015 1:39:52 PM | A | PASS |
|
|
|
ESC14-00771
| General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 1:17:33 PM | | CANC |
|
|
|
ESC14-00799
| General Inspection | 6/18/2015 | 6/19/2015 | 6/19/2015 1:16:26 PM | A | PASS |
|
|
WIP. No violations.
|
ESC15-00030
| Aging Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 11:57:49 AM | | PASS |
|
|
Near completion. Some housekeeping required before permit final. No sediment leaving site at time of inspection. Approved.
|
ESC14-01083
| General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 11:05:41 AM | | PART |
|
|
Site in good condition. No runoff or sediment leaving site. No fugitive dust.
Just need to install lined concrete washout for the new townhomes that have just started.
|
ESC15-00613
| Site Preparation | 6/18/2015 | 6/19/2015 | 6/19/2015 10:58:38 AM | P | PASS |
|
|
###-#### Inspection requested via web by Erby Gonzales
1 of 2 new Barber Valley Townhomes- excavation approved, BMPs installed.
-need to designate lined concrete washout in coordination with Brighton Corp. prior to foundation work.
|
ESC15-00614
| Site Preparation | 6/18/2015 | 6/19/2015 | 6/19/2015 10:58:10 AM | P | PART |
|
|
###-#### Inspection requested via web by Erby Gonzales
1 of 2 new Barber Valley Townhomes- excavation approved, BMPs installed.
-need to designate lined concrete washout in coordination with Brighton Corp. prior to foundation work.
|
ESC14-00657
| Random Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 10:39:11 AM | A | PASS |
|
|
River Height's #6 has SFHs in progress. BMPs are installed and no corrections currently needed. Remaining capacity in lined concrete washout. Approved.
|
ESC14-01167
| DOC - Permit Finaled | 6/19/2015 | 6/19/2015 | 6/19/2015 10:32:39 AM | P | PASS |
|
|
Site final and document final. 3 new Harris Crossing townhomes are now complete and stabilized. ESC conditions satisfied.
|
ESC14-01164
| DOC - Permit Finaled | 6/19/2015 | 6/19/2015 | 6/19/2015 10:31:17 AM | P | PASS |
|
|
Site final and document final. 3 new Harris Crossing townhomes are now complete and stabilized. ESC conditions satisfied.
|
ESC14-01163
| DOC - Permit Finaled | 6/19/2015 | 6/19/2015 | 6/19/2015 10:30:26 AM | P | PASS |
|
|
Site final and document final. 3 new Harris Crossing townhomes are now complete and stabilized. ESC conditions satisfied.
|
ESC14-01171
| Aging Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 10:21:30 AM | | PASS |
|
|
Home complete, needs landscaping. No corrections
|
ESC14-01035
| General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 10:10:29 AM | | PASS |
|
|
Home construction is complete and owners have moved in. Bond issued for revegetation and stabilization.
Stockpile will be removed by Central Paving and yard will be landscaped, culdesac swept thoroughly.
No sediment runoff issues or hillside erosion observed. Permit will stay open to monitor site until stabilization is acheived
|
ESC15-00094
| Complaint Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 10:05:02 AM | A | PART |
|
|
RP from JH Development reported a complaint he received regarding BMPs at Boulder Heights #6
Site is currently inactive and will be for the next 3-4 weeks, when Central Paving will return to complete work.
New BMPs installed include: - J shaped sandbag sediment containment at Windsong and Birdsong - Restricted entrance; using paved surface as stabilized entrance and closed Windsong at Birdsong - Wattle was maintained at SE limit of disturbance to contain sheet flow sediment. No issues or breeches observed.
Corrections needed: 1. Install filter or manhole plugs to keep dirt out of sewer on Windsong entrance 2. Move stockpile away from manhole and street 3. Perform sweeping and cleaning of the sidewalk, street, and gutter on the paved portion of Windsong. 4. Pick up any litter on site 5. Install wattle above newly constructed drainage pipe outlet and rip rap to contain sediment from the distuberd area of the outlet.
Overall site is in good condition, no significant trash issues, no trackout, no fugitive dust occuring.
Will reinspect end of next week 6/25
|
ESC14-00799
| BMP Violation | 6/18/2015 | 6/19/2015 | 6/18/2015 4:32:31 PM | A | CANC |
|
|
data entry error
|