PDS Online
Making
Boise
the most livable city in the country.
Home
Permits
Search by Permit Number
How to search by permit number
Search by Address
Search by Customer Number
Search by Current Planning Number
Search in Project by Permit Number
Search by Project Name
Inspections
Search by Permit Number
Search by Request Date
Search by Company Name
Fees
Impact Fees Estimate Calculator
Other Searches
Search for Licensed Contractors
Search Parcel by Address
Search Historical Surveys
Reports
Daily Reports
Weekly Reports
Monthly Reports
Home
/
Inspections
/
Inspector Activity
Inspections for the day of:
Tuesday, June 19, 2018
.
Number of inspections:
13
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Andy J. Long
Title
EROSION INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC15-01210
General Inspection
6/18/2018
6/19/2018
6/21/2018 7:51:20 AM
A
PASS
4 active SFHs, 1 pool under construction. Permitted seperately. No issues with lots under subdivision developer control. Storm drains along Mockbee have remained open to retain all subdivision to Sherman Hollow system.
No corrections requested.
ESC16-01410
General Inspection
6/19/2018
6/19/2018
6/20/2018 12:56:04 PM
CANC
ESC15-01579
Site Final
6/18/2018
6/19/2018
6/20/2018 11:27:08 AM
A
NR
Corrections needed to get ESC final:
- remove wattles still staged/dumped on site.
- complete landscaping between building and Greenbelt and/or get Boise Parks and Rec sign off.
No Pentalon crew found on site. Parcel hold for C of O until corrections are addressed.
ESC17-00018
General Inspection
6/18/2018
6/19/2018
6/20/2018 11:02:02 AM
A
PASS
WIP on SFHs by Blackrock, Hunter Homes, and ZEC. No trackout from sub or work areas, spills, or fugitive dust issues observed. Storm drains have sediment protection.
No corrections requested, approved.
ESC16-01736
Conference
6/18/2018
6/19/2018
6/19/2018 4:58:08 PM
A
PEND
Dirt/dust check
No activity at time of inspection. Working on the sewer connections with an open trench and stockpile in front yard.. Some dirt on the road, no dust at time of inspection.
Called RP to request that road be thoroughly swept once excavation is complete and backfilled. He said it will be done and cleaned up this week. Follow up scheduled for Friday 6/22.
ESC18-00356
Site Final
6/19/2018
6/19/2018
6/19/2018 3:46:01 PM
P
NR
Need to complete landscaping/stabilization with the ground cover as discussed. Remove silt fence and remove DI bags on 4th and Myrtle and 5th & Broad. Corrections issued onsite to Tanner with ESI
ESC12-00403
General Inspection
6/19/2018
6/19/2018
6/19/2018 2:48:55 PM
PASS
ESC17-01196
General Inspection
6/19/2018
6/19/2018
6/19/2018 11:58:27 AM
A
PART
Culdesac is clean with no trackout. No sediment overflow observed in gutter below silt fence.
Corrections are needed. RP/GC Matt on site to review corrective actions.
- remove full DI bag at end of Santa Paula due to potential for overflow leading to hillside erosion. No new drop inlet insert is required, instead RP will install a wattle section around outside of inlet and weigh down so flush with pavement.
- install slope interupting wattles along the north side of house (between neighbor and garage) where water if flowing down slope to steep to bank above Santa Marian
- empty full trash container
- plan on removal of silt fence or remove captured dirt to extend life span of silt fence.
Will check for completion of first two corrections 6/21 PM
ESC17-00623
Aging Inspection
6/19/2018
6/19/2018
6/19/2018 11:21:18 AM
CANC
ESC16-01472
Conference
6/19/2018
6/19/2018
6/19/2018 11:16:25 AM
P
FAIL
Stormwater runoff from construction site and additional flows from Shaw Mtn. Road flowed down the Logan alley ROW and deposited some eroded sediment onto property at 1010 Floral
Correction request:
- begin clean and removal of sediment on grass and scrape bottom of Logan. Refresh construction entrance rock.
- street sweeping on Logan and Floral after mud dries
- install more durable wattle (gatorguard) that can be installed across Logan to direct any flow away from 1010 Floral to the grass area by Shaw Mtn Apartments.
- at lowest terraced staging area, a sandbag or other diversion/conveyance barrier will capture flow from above and send to the leveled area rather than down Logan.
- repair and re-install wattles where water passed under. Remove captured sediment.
- install tempory roof gutter system to send water to the seepage bed rather than flowing off roof to ground.
RP-GC onsite. Syman Company and other corrections must be started today. Notified ACHD that there is evidence of more flow from Shaw Mtn on the Logan ROW section.
ESC18-00546
Site Preparation
6/18/2018
6/19/2018
6/19/2018 8:29:11 AM
A
CANC
ESC17-00680
General Inspection
6/19/2018
6/19/2018
6/19/2018 7:40:59 AM
CANC
ESC17-00681
General Inspection
6/19/2018
6/19/2018
6/19/2018 7:40:43 AM
CANC