ESC16-01659
| Aging Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 9:56:02 AM | | CANC |
|
|
|
ESC17-00836
| Site Final | 6/20/2018 | 6/20/2018 | 6/21/2018 9:55:38 AM | P | CANC |
|
|
|
ESC17-01491
| General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 9:46:43 AM | P | FAIL |
|
|
Bridge is complete, but not yet open WIP on park monument sign. Shoulders and banks have had a seed and tacifier application. No temp BMPs left in creek, trash around banks is picked up.
Corrections needed:
- remove downed section of SF on NW side of bridge along creek. Install new sediment barrier/buffer below the bank - remove BMPs installed in basin between Warm Springs bypass and pathway. - check erosion observed on shoulds of road between bypass and bridge, may need additional stabilization - pay outstanding special investigation fees to the PDS permit desk
|
ESC18-00264
| General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 8:20:02 AM | P | FAIL |
|
|
Permit sign posted, some wattles installed around site. GC-RP Jeff on site.
Minimal stabilzation and erosion controls (slope interupting wattles, perimter wattles) on slopes below home and around unfinished driveway. Road has had sediment runoff and sandy trackout.
Correction: - sweep up trackout at entrance, coordinate with adjacent site to clean up accumulated sediment around storm drain at bottom of hill - review ESC plan and install wattles and other controls. - use rock check dams instead of wattle check dams to slow runoff from driveway and trap sediment
Jeff agreed that slopes need more control and that next week landscaping and BMP installation will occur. Will review ESC site plan on site wth Jeff on Friday and check for clean up.
|
ESC18-00171
| General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 8:11:27 AM | P | PART |
|
|
Silt fence perimeter working well to contain sediment. Vegetation on slope below excavation has been preserved. Permit sign posted.
Evidence of trackout and sediment runoff from access drive in combination with adjacent site.
Correction: - sweep up accumulated sediment around inlet at bottom of hill. Coordinate with adjacent project RP. - install runoff controls on driveway between home site and where joining other homes driveway.
Notified GC Noah
|
ESC18-00310
| General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 7:49:39 AM | P | PASS |
|
|
WIP on two adjacent Canyon Crest homes. 3rd lot being used for concrete washout, which is lined and away from sidewalk. Permit signs posted. No trackout.
Correction needed: - install wattle or silt fence below stockpile to prevent runoff to washout and street.
Notified RP-GC Dave
|
ESC18-00309
| General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 7:49:22 AM | P | PART |
|
|
WIP on two adjacent Canyon Crest homes. 3rd lot being used for concrete washout, which is lined and away from sidewalk. Permit signs posted. No trackout.
Correction needed: - install wattle or silt fence below stockpile to prevent runoff to washout and street.
Notified RP-GC Dave
|
ESC18-00440
| General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 7:41:58 AM | P | PASS |
|
|
WIP. No trackout or discharges observed. Trash contained.
Areas used to access pool will need revegetation/stabilzation
|
ESC16-01553
| Site Final | 6/20/2018 | 6/20/2018 | 6/21/2018 7:38:55 AM | P | PASS |
|
|
Home complete and landscaped. Permit open for stabilization of lots used for access and staging.
On the lot below RP installed perimeter wattles and lot has vegetated. Upper lot has install controls by the parcel owner.
ESC permit conditions satisfied.
Lots will be monitored under main Sherman Hollow subdivision permit.
|
ESC14-01083
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 12:14:15 PM | | PASS |
|
|
|
ESC17-01389
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 11:15:59 AM | P | PASS |
|
|
WIP on foundation and site work. Construction entrance and perimeter BMPs in good condition. Lined concrete washout on site.
No trackout or fugitive dust observed. Approved.
Duplicate ESC permit, ESC18-00194 has been closed.
|
ESC18-00194
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 11:15:06 AM | P | PASS |
|
|
WIP on foundation and site work. Construction entrance and perimeter BMPs in good condition. Lined concrete washout on site.
No trackout or fugitive dust observed. Approved.
See also ESC17-01389
|
ESC18-00194
| DOC - Permit Finaled | 6/20/2018 | 6/20/2018 | 6/20/2018 11:14:09 AM | P | PASS |
|
|
ESC inspections for Aspen Valley will be entered under main ESC site permit that was issued with GRD permit. See ESC17-01389. This permit closed.
|
ESC15-01288
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 10:47:56 AM | | PASS |
|
|
Most homes now constructed, common areas landscaped and stabilized. Concrete washout and storm drain protection still installed on site for active projects. No trackout from sub, excessive dust, loose trash or other issues observed.
Follow up on Alturas Homes on Spotted Horse: drainage channel/catchment behind homes is has been installed, finished homes have gravel/rock stabilization. Two homes not yet stabilzed. No new issues reported from neighbor on Glacier. Tim with Alturas noted they will be finishing homes in July and will stabilize channel and clean up sediment deposited at occupied home located downhill from from the active sites.
|
ESC17-01109
| Site Final | 6/20/2018 | 6/20/2018 | 6/20/2018 10:38:39 AM | P | PASS |
|
|
Home complete, landscaped, and occupied. Temp BMPs for subdivision to remain for continuing construction.
|
ESC17-01056
| Site Final | 6/20/2018 | 6/20/2018 | 6/20/2018 10:38:25 AM | P | PASS |
|
|
Home complete, landscaped, and occupied. Temp BMPs for subdivision to remain for continuing construction.
|
ESC17-00725
| Site Final | 6/20/2018 | 6/20/2018 | 6/20/2018 10:36:37 AM | P | PASS |
|
|
Home complete, landscaped, and stabilized. No ESC corrections, permit finaled.
|
ESC17-01404
| Site Final | 6/20/2018 | 6/20/2018 | 6/20/2018 10:35:01 AM | P | PASS |
|
|
ESC permit conditions satisfied. Lansdcaped and stabilized. No ESC corrections.
|
ESC17-01100
| Site Final | 6/20/2018 | 6/20/2018 | 6/20/2018 10:34:01 AM | P | PASS |
|
|
Home complete and landscaped. Drainage channel behind home is lined. No ESC corrections.
|
ESC16-01650
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 10:23:55 AM | A | PEND |
|
|
Corrections completed:
- silt fence has been removed and dirt filled into gully that eroded above silt fence between wattles. - Dirt that was behind sediment has moved off slope.
Corrections needed; - section of wattle that is still installed needs maintenance and more stakes. There is a low spot where overflow could occur - slope still not vegetated
Note: SFH sites on rim are working on perimter wattle installation, see ESC17-01298
http://pdsonline.cityofboise.org/pdsonline/details.aspx?id=ESC17-01298
|
ESC17-00682
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 10:12:35 AM | | PASS |
|
|
WIP. Multiple homes on this section all in final stages. No trackout or discahrges. Storm drain has sediment protection. Trash contained.
|
ESC17-00687
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 10:07:07 AM | | CANC |
|
|
|
ESC16-01253
| General Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 10:06:38 AM | | CANC |
|
|
revegetation phase. no inpsection
|
ESC17-01298
| Conference | 6/19/2018 | 6/20/2018 | 6/20/2018 10:06:20 AM | A | DONE |
|
|
Meeting with Mike with Proscape Landscaping (208.514.7457) to provide training and BMP flip guide on wattle installation.
Meeting with Mike with ProVision Landscaping (208.514.7457) to provide training and BMP flipguide on wattle installation. 9 AM
required installation specifications: - 8 " wattle - set wattle in 2-3" deep half circle trench along countour/perimeter (within 1 ft of fence line) - stake wattles at ends and at 4-5 intervals in between. Adjoining sections should be overlapped 6" and staked tightly together - backfill trench dirt on upslope side of wattle
Provided BMP booklet and RP manual. Mike will enroll in class as well
Follow up scheduled Friday 6/22 PM
|
ESC17-01444
| Conference | 6/19/2018 | 6/20/2018 | 6/20/2018 10:06:20 AM | A | DONE |
|
|
Meeting with Mike with ProVision Landscaping (208.514.7457) to provide training and BMP flipguide on wattle installation. 9 AM
required installation specifications: - 8 " wattle - set wattle in 2-3" deep half circle trench along countour/perimeter (within 1 ft of fence line) - stake wattles at ends and at 4-5 intervals in between. Adjoining sections should be overlapped 6" and staked tightly together - backfill trench dirt on upslope side of wattle
Provided BMP booklet and RP manual. Mike will enroll in class as well
|
ESC17-00624
| Aging Inspection | 6/20/2018 | 6/20/2018 | 6/20/2018 8:14:59 AM | | PASS |
|
|
Pool completed in 2017. No ESC issues; BLD still open.
|
ESC17-00624
| DOC - Permit Finaled | 6/20/2018 | 6/20/2018 | 6/20/2018 8:14:25 AM | P | PASS |
|
|
|
ESC16-01457
| General Inspection | 6/13/2018 | 6/20/2018 | 6/19/2018 10:33:49 AM | A | PASS |
|
|
Perimeter wattles and 1 section of slope interupting wattle has been installed. No sediment runoff to sidewalk, but some erosion has occured on the driveway section.
Need to finish landscaping and stabilization of that slope and address runoff from the upper lot down to the access drive.
Notified homeowner via text message. Will check back next week.
|