Inspections for the day of: Tuesday, June 7, 2016.
Number of inspections: 24
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00857 General Inspection6/7/20166/7/20166/9/2016 12:13:57 PM PASS
Superior Construction now active onsite at Eyrie Canyon. Water truck on site and operating full time to limit dust from the tractor traffic. No plumes exiting area of construction.

Hillsides are well vegetated and crew is aware of ESC concerns at the site.

New construction entrance installed per site modifacation/variance to add access at Eyrie Way. Permit sign now also posted in this location and DI bags are installed.

RP available for review of BMPs. No corrections at this time.
ESC15-01161 General Inspection6/7/20166/7/20166/9/2016 11:36:09 AM PART
WIP on interior. Driveway and landscaping not yet installed. No trackout, no discharges at time of inspection.

Sprinkler line blow out caused sediment runoff underneath silt fence at bottom of site. Wallboard waste pile has some peices on sidewalk - need to contain to avoid crushing.

Request to work with EC #7 permittee to change out all DI bags on Bent Bow.
ESC15-01067 Aging Inspection6/7/20166/7/20166/8/2016 11:17:11 AM PASS
minimal activity. WIP. No violations.
ESC15-01026 Aging Inspection6/7/20166/7/20166/8/2016 10:50:49 AM PASS
Home complete and landscaped. BLD open for interior issues. No further ESC inspections required.
ESC15-01210 General Inspection6/7/20166/7/20166/7/2016 4:33:29 PMPPART
Thunder shower at site created some turbid runoff.

Correction request to clean out down stream DI filter bags and install some sediment control check dams to prevent sediment laden water from flowing from the dirt area to the impervious street.

RP stated Syman Co. will do cleanup work today. Will check back for conditions.
ESC15-00033 Site Final6/6/20166/7/20166/7/2016 2:52:23 PMAPEND
ESC16-00693 Site Preparation6/7/20166/7/20166/7/2016 2:50:48 PMPPASS
Permit sign postsed in window. Flat lot, paved driveway access to work area. No MS4 inlets on this section of Hansen. Approved
ESC15-00931 General Inspection6/7/20166/7/20166/7/2016 2:40:10 PM CANC
ESC15-00306 General Inspection6/7/20166/7/20166/7/2016 2:27:51 PM PASS
WIP on final landscaping and park features. Ponds filling with water. Quinn's Pond beach park open to public. No trackout, discharges, or fugitive dust observed. DI bags on WW Blvd still installed, trackout controls removed since access roads are now paved.
ESC15-01314 Aging Inspection6/7/20166/7/20166/7/2016 2:17:14 PM CANC
rescheduled for site final
ESC16-00201 Site Final6/7/20166/7/20166/7/2016 2:12:33 PMPPASS
Final walk through conducted. All MS4 inlets on Capitol/Vista curve have been removed. Sidewalk and gutter swept. Staging area removed and no materials remaining on site. ESC permit conditions satisfied. Stairway with construction barricade will have railing installed next week.
ESC15-00894 General Inspection6/7/20166/7/20166/7/2016 12:49:33 PM CANC
ESC15-01189 Aging Inspection6/7/20166/7/20166/7/2016 12:37:26 PM PASS
Work complete. Site cleaned. No ESC corrections needed. Permit finaled.
ESC15-01189 DOC - Permit Finaled6/7/20166/7/20166/7/2016 12:37:02 PMPPASS
ESC15-00862 General Inspection6/7/20166/7/20166/7/2016 12:33:28 PM PASS
ESC15-00776 General Inspection6/7/20166/7/20166/7/2016 12:31:11 PM PASS
Home near completion. Will need site final walk through to close permit. Make sure no windblown trash on hillside below. No loose fines in gutter/sidewalk.
ESC04-00421 DOC - Permit Finaled6/7/20166/7/20166/7/2016 12:16:16 PMPPASS
old expired permit in database. no inspection
ESC15-00745 Random Inspection6/7/20166/7/20166/7/2016 11:52:33 AMPPART
Construction entrance & silt fence perimter BMP installed. Water truck on site to control fugitve dust.

Corrections requested to RP Dawn:
- have contractor post SWPPP info and Boise ESC permit. (stated that job trailer to be brought on site today)
- schedule site prepartaion inspection with on-site SWPPP inspector/RP Arn next week.

No trackout or discharges, no dust plumes crossing property lines.

Will check in later this week.
ESC15-01033 Site Final6/7/20166/7/20166/7/2016 11:18:05 AMPPASS
Project complete. Site landscaped and stabililzed. All construction materials and loose sediment cleaned, no BMPs left on site or MS4. ESC permit conditions met; all permits finaled.
ESC15-00667 General Inspection6/7/20166/7/20166/7/2016 11:08:10 AM PEND
VM left to RP Garry at Central Paving to provide schedule of temp. BMP removal ( silt fences along the drainage ditches). Out of office till next Monday.
ESC16-00338 Site Preparation6/7/20166/7/20166/7/2016 11:00:50 AMAPASS
Site walk through with RP JC Murray complete. Site is within Riverstone school campus. Building footprint to be excavated below exisng asphalt. Construction access through parking lot of Lysted. Drainage from site will flow to onsite vegetated swale. Yellow permit sign onsite.

Approved for construction.
ESC16-00693 Site Preparation6/6/20166/7/20166/7/2016 10:06:42 AMACANC
Chris Phone #: ###-####

Approved to start. Will inspect in afternoon
ESC12-00403 General Inspection6/7/20166/7/20166/7/2016 9:51:30 AM PASS
ESC15-01033 Aging Inspection6/7/20166/7/20166/7/2016 9:06:15 AM PASS