ESC15-00556
| General Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 12:13:32 PM | | CANC |
|
|
no inspection conducted, site is currently inactive for subdivision devepment
|
ESC15-00403
| General Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 12:12:55 PM | | PASS |
|
|
No trackout. Vegetated perimeter is undisturbed. Working on the interior. Site infrastructure already installed.
|
ESC15-01224
| General Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 12:03:52 PM | | PASS |
|
|
|
ESC15-01468
| Aging Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 11:08:54 AM | | PASS |
|
|
Project complete and stabilized. All permits finaled.
|
ESC15-01437
| Aging Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 8:10:18 AM | | CANC |
|
|
rescheduled
|
ESC14-00886
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 2:23:25 PM | | CANC |
|
|
|
ESC15-01345
| Aging Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 2:14:38 PM | | CANC |
|
|
rescheduled for next week
|
ESC15-01343
| Aging Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 2:11:57 PM | | CANC |
|
|
rescheduled for next week
|
ESC15-00541
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 2:06:12 PM | | PASS |
|
|
No activity at site. No violations. Access road and utilities are installed. Some loose sediment within site, but not runoff issues. No corrections at this time.
|
ESC11-00879
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 1:57:37 PM | | PART |
|
|
Need to sweep curb and gutter due to trackout and loose dirt from SFH construciton. No dirt coming outside of subdivision to Boise Hills Dr and onsite inlets have sediment protection. Just needs house cleaning.
|
ESC15-01283
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 1:56:23 PM | | PASS |
|
|
Near completion. Getting prepped for landscaping. No discharges or trackout from site observed.
|
ESC16-00412
| Site Preparation | 6/8/2016 | 6/9/2016 | 6/9/2016 1:33:24 PM | A | PASS |
|
|
Jim Phone #: ###-####
Permit sign posted on fence - visible from road. Access will be from dirt alley. Site has good drainage/vegetation that will be preserved for onsite stormwater retention. Approved.
|
ESC15-01473
| Aging Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 1:22:03 PM | | PASS |
|
|
|
ESC16-00403
| Site Preparation | 6/9/2016 | 6/9/2016 | 6/9/2016 1:10:54 PM | P | PASS |
|
|
Jill Phone #: ###-####
BMPs installed including sediment control mats on DIs, perimeter wattle along the south border, and construction fencing with dust screens.
Permit posted. Approved for demolition. Water supply to be onsite to control dust.
|
ESC14-01063
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 12:18:57 PM | P | PASS |
|
|
No activity in EC #8. All DIs on Goshawk and Arrow Villa have been cleaned this week. Hillside vegetation and silt fence perimeter at runoff point are in good condtion and should contain sediment onsite. Lots that were under water have been re-graded and SFH construction should begin soon.
No corrections, site is in compliance. Permit and SWPPP info onsite.
|
ESC13-00764
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 12:16:13 PM | P | PART |
|
|
WIP on SFHs on Bent Bow in EC #7. Lined concrete washout pit is located at bottom of hill on Arrow Villa.
Correction request to developer and Canyon Crest Homes:
-all DI bags on Bent Bow need to be emptied out and reisntalled.
No other corrections. Hillsides well vegetated. Individual projects are mostly clean.
|
ESC14-00432
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 10:07:50 AM | | CANC |
|
|
|
ESC15-00871
| Complaint Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 10:06:44 AM | A | PASS |
|
|
Dust complaint received:
Water supply and hoses on site for dust control. Requested that in afternoon need to spray down stockpiles.
BMPs installed on site, DIs have sediment filters, lined concrete washout area is provided.
Requested that trash bin be used. Hauling off materials as they go. No windblown trash across street or along canal.
Permit sign posted. No dust at time of inspection.
|
ESC16-00428
| Site Preparation | 6/8/2016 | 6/9/2016 | 6/9/2016 9:20:21 AM | A | PASS |
|
|
Call me 30 prior to the inspection is you would like to meet me on site. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
Direct power line bury. Low risk flat site. Will notify when complete. Approved for construction.
|
ESC13-00806
| General Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 9:16:34 AM | | PASS |
|
|
|