Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC19-00114 Complaint Inspection6/28/20197/1/20197/2/2019 4:13:18 PMPPART
Minor trackout. Sidewalk is now temporarily closed. Trash contained. No spills or discharges.

Site needs to improve on daily sweeping. Will notify builder.
ESC17-01595 General Inspection7/1/20197/1/20197/2/2019 4:08:58 PM PASS
No trackout or discharges. Down gradient sediment controls installed. Trash contained. Approved.
ESC19-00082 General Inspection7/1/20197/1/20197/2/2019 3:59:29 PMPPASS
Excavation appears complete. Sidewalk, gutter, and street are clean. No corrections needed at this time.
ESC19-00402 General Inspection6/27/20197/1/20197/2/2019 3:58:32 PMAPART
Dustin Collins
###-####

Road was swept but wattles still not installed properly.

Will follow up with contractor next week for correct installation.
ESC19-00778 Site Final7/1/20197/1/20197/1/2019 4:25:28 PMPPASS
Demo complete. No debris left on site, site graded inward to contain stormwater and runoff. ESC permit finaled.
ESC17-00406 Site Final7/1/20197/1/20197/1/2019 4:13:24 PMPNR
Some minor landscaping, alley paving, and exterior clean up remaining. Temporary DI sediment bag installed at 10th and Washington needs to be removed.

Will follow up with contractor next week.
ESC17-01473 General Inspection7/1/20197/1/20197/1/2019 4:07:07 PM PASS
ESC19-00398 Complaint Inspection7/1/20197/1/20197/1/2019 3:58:27 PMPFAIL
Site is not yet contained due to large excavation required. Loose dirt and no sediment barrier along the common drive.

Correction request to sweep loose material off common drive. Meeting scheduled with RP to go over BMPs needed now that the intial footprint has been excavated.

ESC19-00735 General Inspection7/1/20197/1/20197/1/2019 3:33:13 PMPPASS
Demo phase complete. Site is cleaned up well, no debris or stockpiles. Flat site. Will keep open for monitoring until next phase permits are pulled.
ESC19-00736 Random Inspection7/1/20197/1/20197/1/2019 3:32:59 PMPPASS
Demo phase complete. Site is cleaned up well, no debris or stockpiles. Flat site. Will keep open for monitoring until next phase permits are pulled.
ESC18-00290 Aging Inspection7/1/20197/1/20197/1/2019 11:25:21 AM CANC
ESC18-00290 DOC - Permit Finaled7/1/20197/1/20197/1/2019 11:25:18 AMPPASS
ESC18-01530 General Inspection6/28/20197/1/20197/1/2019 11:25:01 AMAPEND
RP has corrections being addressed this week.
ESC19-00241 Conference7/1/20197/1/20197/1/2019 11:23:35 AMAPASS
site walk-through and BMP inspection scheduled for next Tuesday AM.

Permit sign posted on site. Crews will begin to remove trees and playground asphalt this week. Perimter vegetation will remain preserved. RP on duty.

Building demolition to begin next week.
ESC17-01439 General Inspection7/1/20197/1/20197/1/2019 11:20:50 AM CANC
ESC17-01488 General Inspection7/1/20197/1/20197/1/2019 11:20:06 AM CANC