ESC14-00135
| General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 3:54:58 PM | | PEND |
|
|
Landscaping in progress. Will clean culdesac was yard is complete.
|
ESC15-00094
| Tracking Control | 7/10/2015 | 7/13/2015 | 7/13/2015 3:43:44 PM | A | PASS |
|
|
Areas affected by sediment deposits have been swept. Additional controls installed. Road will soon be paved.
Sweeper still onsite to clean another time. No new corrections.
|
ESC14-00921
| Aging Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 3:32:53 PM | | PASS |
|
|
No activity. No violations. Permit not yet expired, will be next general inspection.
|
ESC15-00023
| BMP Violation | 7/10/2015 | 7/13/2015 | 7/13/2015 3:20:18 PM | P | FAIL |
|
|
Wattles installed but sidewalk and gutter are still dirty.
Concrete washout spilled on sidewalk and not contained. No trash container.
Re-inspection fee charged. Multiple violations without adequate corrective actions.
|
ESC13-00684
| General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 2:45:45 PM | | PART |
|
|
WIP on SFHs in Antelope Springs. Workers parking on pavement to prevent trackout. No trackout.
Hillside and canal bank has vegetated and stabilized nicely along northside.
Correction:
Need to change out DI bags which are near 50% full.
|
ESC15-00773
| Site Preparation | 7/10/2015 | 7/13/2015 | 7/13/2015 1:38:42 PM | P | PASS |
|
|
Grant Phone #: ###-####
Site is prepared for excavation. 1 of 3 new SFHs adajacent to eachother in new unoccupied subdivision. Lined concrete washout pit provided. Permits posted.
|
ESC15-00774
| Site Preparation | 7/10/2015 | 7/13/2015 | 7/13/2015 1:38:23 PM | P | PASS |
|
|
Grant Phone #: ###-####
Site is prepared for excavation. 1 of 3 new SFHs adajacent to eachother in new unoccupied subdivision. Lined concrete washout pit provided. Permits posted.
|
ESC15-00775
| Site Preparation | 7/10/2015 | 7/13/2015 | 7/13/2015 1:38:09 PM | P | PASS |
|
|
Grant Phone #: ###-####
Site is prepared for excavation. 1 of 3 new SFHs adajacent to eachother in new unoccupied subdivision. Lined concrete washout pit provided. Permits posted.
|
ESC14-01083
| BMP Violation | 7/10/2015 | 7/13/2015 | 7/13/2015 12:50:22 PM | A | PEND |
|
|
Check that trash has been picked up.
Site perimeter fence is not up yet. Some litter was collected but swale still needs further clean up and a trash enclosure.. Notice given Brighton to continue clean up and install fence and trash container. Need to be in place by Wednesday.
|
ESC13-00755
| General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 12:32:40 PM | | PASS |
|
|
No trackout or discharges from Terraces site observed. Streets and gutter free of significant amounts of sediment and DI bags are installed. The silt fence will soon be removed as landscaping is completed behind the condo units. No blowouts to alley way occuring.
No corrections at this time.
|
ESC15-00556
| Tracking Control | 7/10/2015 | 7/13/2015 | 7/13/2015 12:28:22 PM | A | PART |
|
|
Warm Springs at Highland Valley has been swept and temporary retaining holes/diversion have been built along Highland Valley lining the new EV phase.
Tao and Boven culdesac has been cleaned and DI bags changed.
Need to have sweeper come do another round as the dirt loosens.
|
ESC15-00621
| Tracking Control | 7/13/2015 | 7/13/2015 | 7/13/2015 11:36:49 AM | P | FAIL |
|
|
Correction notice:
- clean up mud and illicit concrete washout - move stockpiles further into site - pick up and contain trash and materials - sweep Lindsay Street
|
ESC14-01156
| General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 9:49:34 AM | | PASS |
|
|
Communications tower is complete. Disturbed areas stabilized. All permits finaled.
|
ESC14-01156
| DOC - Permit Finaled | 7/13/2015 | 7/13/2015 | 7/13/2015 9:48:44 AM | P | PASS |
|
|
|
ESC13-00294
| Aging Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 9:14:57 AM | | PASS |
|
|
|
ESC15-00006
| General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 8:41:40 AM | | PASS |
|
|
WIP. Permit posted on fence. No trackout or discharges observed. No corrections.
|