Inspections for the day of: Friday, July 17, 2020.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-01167 General Inspection7/17/20207/17/20207/22/2020 4:33:54 PMPPASS
Vertical construction in progress. No trackout or discharges from site. No fugitive dust observed. Perimeter is clean and has sediment controls installed. No corrections at this time.
ESC18-01168 General Inspection7/17/20207/17/20207/22/2020 4:33:39 PMPPASS
Vertical construction in progress. No trackout or discharges from site. No fugitive dust observed. Perimeter is clean and has sediment controls installed. No corrections at this time.
ESC19-00917 Aging Inspection7/17/20207/17/20207/21/2020 12:57:41 PM PASS
Demo complete. Area used by Layton Construction for staging for the NW parking garage and shipping/receiving facilty. See ESC18-01167-68
ESC20-00697 Site Final7/17/20207/17/20207/17/2020 3:24:30 PMPPASS
See ESC20-01159. This project complete. BLD still open
ESC20-00066 Site Final7/17/20207/17/20207/17/2020 3:24:03 PMPPASS
See ESC20-01159. This project complete. BLD still open
ESC20-00554 BMP Violation7/17/20207/17/20207/17/2020 3:02:44 PMPPASS
compliance inspection. RP states corrections have been completed.

Dumped concrete washout slurry and rock has been cleaned up as requested. Fee for violation has been paid. RP called for an inspection. Approved. Parcel hold removed.

Will inspect next week for a liquid waste/rinsing station/receptacle
ESC19-00995 Site Final7/17/20207/17/20207/17/2020 2:54:20 PMPPASS
Phase of KAP improvements complete. No disturbed area remaining, no loose dirt in parking lot, no equipment on site. ESC permit conditions satisfied.

Phase 2 will include parking lot renovation and storm drain improvements. McMillan Jacobs with Jerry and Greg will also be contractor for this phase.
ESC19-01078 Site Final7/17/20207/17/20207/17/2020 12:44:07 PMPPASS
ESC19-00890 Site Final7/17/20207/17/20207/17/2020 12:43:46 PMPPASS
Wolf Tree Square BMPs to remain installed for ongoing townhome construction
ESC19-00913 Site Final7/17/20207/17/20207/17/2020 12:43:31 PMPPASS
Wolf Tree Square BMPs to remain installed for ongoing townhome construction
ESC19-01078 Aging Inspection7/17/20207/17/20207/17/2020 8:20:56 AM CANC
ESC19-01193 Aging Inspection7/17/20207/17/20207/17/2020 8:20:23 AM CANC
ESC19-00890 Aging Inspection7/17/20207/17/20207/17/2020 8:19:47 AM CANC
ESC19-00913 Aging Inspection7/17/20207/17/20207/17/2020 8:19:30 AM CANC
ESC19-00193 General Inspection7/17/20207/17/20207/17/2020 8:18:02 AM CANC
see ESC19-00181
ESC19-00194 General Inspection7/17/20207/17/20207/17/2020 8:17:41 AM CANC
see ESC19-00181
ESC19-00191 General Inspection7/17/20207/17/20207/17/2020 8:14:12 AM CANC
see ESC19-00181
ESC19-00190 General Inspection7/17/20207/17/20207/17/2020 8:13:52 AM CANC
see ESC19-00181
ESC20-01159 Site Preparation7/17/20207/17/20207/17/2020 12:00:00 AMPPASS
Dillon - */Screened*/ Phone #: ###-####

Initial BMPs installed including construction entrance, SWPPP signage, and storm drain inlet sediment protection.

Will use ecopan for concrete washout and there is a water truck onsite to control fugitve dust.

Approved.