Inspections for the day of: Friday, July 20, 2018.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01196 General Inspection7/20/20187/20/20187/24/2018 12:40:00 PM CANC
rescheduled
ESC18-00114 Site Final7/19/20187/20/20187/24/2018 12:28:28 PMPNR
Project near completion: Yard is landscaped, new driveway poured. BLD is open

ESC actions required prior to ESC site final approval:
- sweep up and clean any loose dirt or sediment tracked out from site onto Wilson
- remove temporary sediment protection bags from strom drains on Wilson
ESC17-01710 General Inspection7/20/20187/20/20187/20/2018 2:22:06 PMPPASS
Infill subdivision installation complete. No SFH construction, no activity. No sediment runoff or dust issues observed.
ESC17-01479 Complaint Inspection7/20/20187/20/20187/20/2018 1:57:42 PMPPEND
No issues on permited site. Crew working on gas line on Pierce Park in front of site. Work is almost complete and crews were sweeping up loose dirt. Some localized dust, but not excessive. Work to be completed today.
ESC18-00612 Site Preparation7/20/20187/20/20187/20/2018 1:52:50 PMPPASS
Addition is framed. No ESC issues at site. Approved.
ESC17-01245 General Inspection7/20/20187/20/20187/20/2018 1:51:38 PMPPASS
Home near completion. Located on private lane. No trackout or losse dirt observed. Site is not yet landscaped. BLD is open.
ESC17-01767 General Inspection7/20/20187/20/20187/20/2018 1:43:37 PMPPASS
Near completion. WIP on interior. Exterior of home complete, but not yet landscaped. No corrections needed.
ESC18-00544 General Inspection7/20/20187/20/20187/20/2018 1:42:53 PMPPASS
WIP on foundation. No violations observed. No activity at time of inspeciton.
ESC17-00817 Site Final7/20/20187/20/20187/20/2018 1:40:28 PMPPASS
Home complete, all permits finaled. No ESC requests. ESC permit conditions satisfied.
ESC17-01205 Site Final7/20/20187/20/20187/20/2018 1:39:01 PMPPASS
Home complete, cleaned up, landscaped, and occupired. No ESC requests, BLD permit is finaled. ESC permit closed out.
ESC17-00763 Aging Inspection7/20/20187/20/20187/20/2018 1:33:34 PM PASS
Home complete, landscaped, and occupied. No temporary BMPs left onsite. ESC permit conditions satisifed.
ESC17-00763 DOC - Permit Finaled7/20/20187/20/20187/20/2018 1:32:45 PMPPASS
ESC17-01182 General Inspection7/20/20187/20/20187/20/2018 12:34:41 PM CANC
ESC17-01479 Complaint Inspection7/20/20187/20/20187/20/2018 12:33:25 PMPCANC
ESC17-01479 Complaint Inspection7/20/20187/20/20187/20/2018 12:33:17 PMPCANC
ESC17-01473 General Inspection7/19/20187/20/20187/20/2018 12:33:04 PMAPASS
No trackout, offsite discharges, or other issues observed. RP on site with SWPPP info and site BMP map available.

Permit info is posted at each entrance. Wattles installed to protect the Punque River are in good conditon. Tree protection fences are installed.

Correction request:

- have Ecopan concrete washouts serviced

Working with Parks and Rec, Suez subcontractor, and Zoo management in regards to the water line work occuring and the flush discharge set up next to Pungwe River area. Status pending.
ESC16-01253 General Inspection7/20/20187/20/20187/20/2018 11:22:01 AM CANC
ESC17-01362 General Inspection7/19/20187/20/20187/20/2018 11:18:37 AMAPASS
9:00 AM

ESC permit sign posted. WIP on vertical construction. No trackout or discharges observed, trash contained. No dewatering occuring at this time, the site will dewater one more with Brown Excavation to tap into a line on the west side of site.