Inspections for the day of: Friday, July 24, 2020.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC19-01388 Aging Inspection7/24/20207/24/20207/24/2020 3:22:52 PM CANC
ESC20-00490 Site Preparation7/24/20207/24/20207/24/2020 3:22:27 PMPFAIL
No site prep requested - RP changed to Jim Jewitt.

Correction requests to JIm:
- install sediment control wattle or silt fence to provide barrier for runof flowing to 26th.
- get spill clean up material for oil leak that occured.
- sweep road in front of home
ESC19-00324 Conference7/23/20207/24/20207/24/2020 3:20:57 PMADONE
10 AM with home builders

Meeting with Sustainable Homes to review work area. Will set up staging area in center lot above the intersection and landscaped sitting area. Request to install silt fence and/or wattle on the downhill edge of this area

Core has the lots on the west side of sub. Staging area is in back corner. RP was installing initial BMPs.
ESC19-00916 General Inspection7/24/20207/24/20207/24/2020 3:18:42 PM CANC
ESC20-00354 General Inspection7/24/20207/24/20207/24/2020 3:18:07 PMPPART
Pump truck did not know location of washout and performed uncontained washout on adjacent construciton site. That construction site is cleaning it up, but met with RP Lazaro to inspect the washout and discuss signage and communication of location of washout to foundation crew foremen and concrete trucks and pumps.

Follow up scheduled
ESC19-01315 General Inspection7/24/20207/24/20207/24/2020 2:41:01 PM PASS
ESC20-00637 Site Preparation7/24/20207/24/20207/24/2020 2:40:48 PMPPASS
RP Paul on duty. Clean site. Posted ESC permit sign. Common driveway has swale installed alongside it and curb/sidewalk trench was dug along Gary. Approved.
ESC19-00453 Aging Inspection7/24/20207/24/20207/24/2020 12:40:37 PM CANC
rescheduled for site final
ESC20-00126 Random Inspection7/24/20207/24/20207/24/2020 12:19:53 PMPPART
Request to relocate portapot and protect storm drain.

Sidewalk and street swept up. Will be replacing sidewalk and gutter in front of home. Warned about concrete washout and protecting storm drain. Follow up scheduled
ESC19-01339 Aging Inspection7/24/20207/24/20207/24/2020 11:53:46 AM PASS
Project near completion, no further excavation/disturbance. No ESC requests.Permit finaled.
ESC19-01339 DOC - Permit Finaled7/24/20207/24/20207/24/2020 11:52:45 AMPPASS
ESC19-01221 Aging Inspection7/24/20207/24/20207/24/2020 11:51:29 AM CANC
rescheduled for site final
ESC19-01223 Aging Inspection7/24/20207/24/20207/24/2020 11:50:41 AM PASS
ESC19-01280 General Inspection7/24/20207/24/20207/24/2020 11:50:20 AM PASS
ESC19-01276 General Inspection7/24/20207/24/20207/24/2020 11:47:19 AM PASS
WIP.. No trackout, dust, discharges, or dumped wsashout observed. Permit sign posted.