ESC15-00762
| General Inspection | 7/28/2016 | 7/28/2016 | 7/29/2016 3:59:13 PM | | PASS |
|
|
DIs protected, no vehicle trackout. Need to continue to improve sweeping of closed lanes on Myrtle and 5th. No spills or discharges observed.
|
ESC15-01210
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 4:16:37 PM | | PASS |
|
|
Temporary stabilzation BMP for erosion has been applied to slopes and is holding together dirt and keeping down dust. Slope interuption wattles throughout site. Sediment controls (perimter wattles & inlet filter bags) installed.
Site in compliance, no activity currently.
|
ESC15-01604
| Aging Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 3:22:40 PM | | PASS |
|
|
|
ESC15-01635
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 3:07:15 PM | P | PASS |
|
|
Mill District Square pation home complete and landscaped. DI bag on Woodcarver to be pulled by Erbie with Brighton. ESC conditions satisfed. Street, sidewalk gutter in front of projects have been cleaned.
|
ESC15-01636
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 3:07:08 PM | P | PASS |
|
|
Mill District Square pation home complete and landscaped. DI bag on Woodcarver to be pulled by Erbie with Brighton. ESC conditions satisfed. Street, sidewalk gutter in front of projects have been cleaned.
|
ESC15-01608
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 3:07:01 PM | P | PASS |
|
|
Mill District Square pation home complete and landscaped. DI bag on Woodcarver to be pulled by Erbie with Brighton. ESC conditions satisfed. Street, sidewalk gutter in front of projects have been cleaned.
|
ESC15-01609
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 3:06:51 PM | P | PASS |
|
|
Mill District Square pation home complete and landscaped. DI bag on Woodcarver to be pulled by Erbie with Brighton. ESC conditions satisfed. Street, sidewalk gutter in front of projects have been cleaned.
|
ESC15-01564
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 3:06:44 PM | P | PASS |
|
|
Mill District Square pation home complete and landscaped. DI bag on Woodcarver to be pulled by Erbie with Brighton. ESC conditions satisfed. Street, sidewalk gutter in front of projects have been cleaned.
|
ESC15-01570
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 3:06:36 PM | P | PASS |
|
|
Mill District Square pation home complete and landscaped. DI bag on Woodcarver to be pulled by Erbie with Brighton. ESC conditions satisfed. Street, sidewalk gutter in front of projects have been cleaned.
|
ESC16-00561
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 2:43:52 PM | P | PASS |
|
|
Excavation crew still onsite removing excess boulders. Boulders being transported up to new SFH site prep work Windsong.
No trackout or discharges. BMPs installed.
|
ESC16-00713
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 2:37:02 PM | P | PASS |
|
|
Foundation complete and site was cleaned afterward. Trash container installed for framers, no sediment runoff. No perimeter wattle currently, may need to install if runoff occurs.
|
ESC15-01391
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 1:40:54 PM | | PASS |
|
|
|
ESC16-00079
| Aging Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 12:02:56 PM | | PASS |
|
|
No earth disturbing activity or loose dirt leaving site. BLD open, no activity since February. No further ESC inspections necessary.
|
ESC16-00079
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 11:57:15 AM | P | PASS |
|
|
|
ESC15-01341
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 11:38:29 AM | | CANC |
|
|
|
ESC16-00273
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 11:26:47 AM | P | PASS |
|
|
Construction complete. ESC conditions satisfied. Hayden Homes to remove all temp BMPs in Aralar once all units complete.
|
ESC16-00246
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 11:26:36 AM | P | PASS |
|
|
Construction complete. ESC conditions satisfied. Hayden Homes to remove all temp BMPs in Aralar once all units complete.
|
ESC15-01642
| Aging Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 11:21:43 AM | | PASS |
|
|
Home complete, front yard landscaped/stabilized and occupied. Active projects occuring on Florida so temp BMPs to stay. ESC permit finaled.
|
ESC15-01642
| DOC - Permit Finaled | 7/28/2016 | 7/28/2016 | 7/28/2016 11:20:48 AM | P | PASS |
|
|
|
ESC16-00176
| Site Final | 7/28/2016 | 7/28/2016 | 7/28/2016 11:06:29 AM | A | PASS |
|
|
|
ESC16-00245
| Site Final | 7/28/2016 | 7/28/2016 | 7/28/2016 11:06:15 AM | A | PASS |
|
|
All storm drain inlets have had temporary BMP sediment filter bags removed by Brett with CBH as requested. No construction materials or equipment on site. Streets and gutters are clean.
All SFHs except one lot in southwest corner is complete - no current plans to build per CBH. All ESC permits in Dunham Commons/Southern Landing are finaled.
|
ESC15-00871
| BMP Violation | 7/27/2016 | 7/28/2016 | 7/28/2016 10:39:00 AM | A | PASS |
|
|
RP swept entire sidewalk frontage, parking lot entrance apron, gutters, and emptied out material in DI bag. Trash and mateials within site was put inside dumpsters.
Approved, corrections complete.
|
ESC15-00339
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 10:18:09 AM | A | PASS |
|
|
Storage structure foundation complete. Very clean perimeter. No trackout to Gage, large Compliance Solutions concrete washout onsite.
No violations, no corrections needed
|
ESC15-01184
| General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 8:30:14 AM | | PASS |
|
|
DI bags installed and with plenty of filtering capacitiy. No trackout to 9th or River, no discharges. Wind blown or tossed litter on 8th Street was picked up as requested. Vertical consruction in progress. No corrections issued.
|