Inspections for the day of: Monday, July 3, 2017.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01372 Site Final6/30/20177/3/20177/5/2017 4:09:24 PMPNR
Work still in progress on clubhouse improvements. Placing rocks along Quinn's Pond.
ESC15-01258 Aging Inspection7/3/20177/3/20177/3/2017 2:51:54 PM PASS
ESC16-00948 General Inspection7/3/20177/3/20177/3/2017 2:50:10 PM CANC
rescheduled 7/5
ESC16-00256 Aging Inspection7/3/20177/3/20177/3/2017 2:37:23 PM PASS
ESC17-00723 Complaint Inspection7/3/20177/3/20177/3/2017 1:04:43 PMPPEND
dewatering with no controls or dewatering plan/permit with ACHD.

ACHD inspector contacted RP, no workers on site. Investigation in progress. No ESC permit sign posted. BMP inspection scheduled for 7/5
ESC16-00430 Site Final7/3/20177/3/20177/3/2017 12:07:21 PMPPASS
No ESC corrections needed at site. Fire station #4 is complete with temp. occupancy. Site is landscaped, storm drainage system installed with south swale hydroseeded and with supplemental irrigation. MS4 on Ustick has had inlet protect removed. ESC permit conditions satisfied.
ESC17-00470 General Inspection6/27/20177/3/20177/3/2017 11:56:40 AMAPASS
NO activity at site, no personnel on site. No wind blown dust issues. No corrections.
ESC17-00499 BMP Violation6/27/20177/3/20177/3/2017 11:47:53 AMAPART
Abram and Coolwater were swept up as requested: No new trackout, no spills or discharges observed.

Correction not completed:

1. Need to provide new concrete washout and clean up old washout.


ESC17-00414 BMP Violation6/27/20177/3/20177/3/2017 11:46:32 AMAFAIL
Corrections not fully completed.

1. Need to provide new concrete washout and clean up old washout.
2. Change out DI bag on Coolwater.


Abram and Coolwater were swept.
ESC15-01171 DOC - Permit Finaled7/3/20177/3/20177/3/2017 11:45:04 AMPPASS
ESC inspections for Spotted Dove now conducted on SFH individual ESC permits. No violations. No further ESC inspections on this permit.
ESC15-01171 Aging Inspection7/3/20177/3/20177/3/2017 11:44:09 AM DONE
ESC17-00571 General Inspection6/27/20177/3/20177/3/2017 11:38:13 AMAPART
Sidewalk and street were swept. DI protection was not chaged out as requested. Will follow up with builder and Spotted Dove subdivision developer Marty
ESC17-00163 Random Inspection7/3/20177/3/20177/3/2017 11:32:39 AMAPASS
No trackout, discharges, or loose trash materials around site. No corrections needed. WIP on interior, not yet landcaped.
ESC17-00164 Random Inspection7/3/20177/3/20177/3/2017 11:32:27 AMPPASS
No trackout, discharges, or loose trash materials around site. No corrections needed. WIP on interior, not yet landcaped.
ESC17-00129 Random Inspection7/3/20177/3/20177/3/2017 11:32:16 AMPPASS
No trackout, discharges, or loose trash materials around site. No corrections needed. WIP on interior, not yet landcaped.
ESC16-01367 DOC - Permit Finaled7/3/20177/3/20177/3/2017 11:29:50 AMPPASS
Earth disturbance complete and stablized. No loose dirt or material, no temporary BMPs aroudn site. No ESC corrections needed. ESC permit finaled.
ESC15-00311 Aging Inspection7/3/20177/3/20177/3/2017 11:23:58 AM PASS
No disturbed area, loose materials or temporary BMPs around existing home remodel. No actviity on BLD since October 2016. Permit expired. NO further ESC inspections.
ESC15-00311 DOC - Permit Finaled7/3/20177/3/20177/3/2017 11:21:39 AMPPASS
ESC16-00725 Site Final7/3/20177/3/20177/3/2017 11:19:20 AMPPASS
Home complete, landscaped, and occupied. No ESC correction requests. DI bag to remain for active project(s)
ESC16-00724 Site Final7/3/20177/3/20177/3/2017 11:18:37 AMPNR
Final landscaping progress in progress. DI bag still installed at north end of Fifeshire culdesac. One open lot remaining, DI bag can be replaced/maintained for new project or removed.
ESC16-01009 Site Final7/3/20177/3/20177/3/2017 11:06:12 AMAPASS
Maverik store complete, landscaped and stabilized. Staging lot to the east of site has had an application of mulch. Stormwater swale installed, DI sediment bag installed on Ustick has been removed. ESC permit conditions satisfied.