ESC17-01346
| General Inspection | 7/8/2019 | 7/8/2019 | 7/12/2019 11:40:49 AM | | PASS |
|
|
|
ESC18-00184
| General Inspection | 7/8/2019 | 7/8/2019 | 7/10/2019 10:11:57 AM | | CANC |
|
|
data entry error
|
ESC19-00371
| Complaint Inspection | 7/8/2019 | 7/8/2019 | 7/9/2019 11:22:08 AM | P | FAIL |
|
|
complaint received 7/5 - dust issues at construction entrance.
notifired RP 7/5 to sweep up all loose dirt on Trent Point to Windsong. Follow up at site.
Corrections needed:
- do maintenance on construction entrance. Rough up rock, add rock, make rock go to edge of Trent Point and lengthen. Prevent truck and works from driving around rock entrance.
- sweep up gutter on Windsong from Birdsong to Trent Point.
|
ESC16-00935
| General Inspection | 7/8/2019 | 7/8/2019 | 7/9/2019 8:01:10 AM | P | CANC |
|
|
|
ESC19-00696
| Site Preparation | 7/8/2019 | 7/8/2019 | 7/8/2019 4:16:05 PM | P | PASS |
|
|
Permit sign posted on temp. power pole. Rock construction entrance installed. No trackout or discharges.
RP Clayton stated that an outpak conrcrete washout will be used for foundation work.
After backfill, the perimeter silt fence along constructiion entrance should be re-installed.
|
ESC19-00402
| Site Preparation | 7/8/2019 | 7/8/2019 | 7/8/2019 4:14:27 PM | P | CANC |
|
|
Dustin Phone #: ###-####
site already started. Rescheduled for site conference to review ESC plan and BMP installations.
|
ESC16-00935
| Complaint Inspection | 7/5/2019 | 7/8/2019 | 7/8/2019 4:10:44 PM | A | PEND |
|
|
report of broken water line and flooding.
Met with downhill homeowner and GC regarding damage from broken water line.
GC will have soils engineer assess slope stability where water has eroded some of the hillside. Excavator was onsite reparing damaged driveway/easement.
Notified PW HIllside. Case pending. Will wait for geotechnical report information for further corrections.
|
ESC18-00920
| Complaint Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 4:06:54 PM | P | FAIL |
|
|
Corrections needed:
Uncontained trash and improperly installed wattle observed. No trackout or discharges
- Properly install perimeter sediment control wattle arouund the stockpile - Collect all loose trash, place in container, and order trash pick up. - Remove bags of quickqrete and garbage from the dried washout pit
Walked site with Roth Home's Cleve. Verbal correction request. follow up scheduled for Thursday 7/11
|
ESC18-00203
| Aging Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 1:58:18 PM | | DEFR |
|
|
inspected by BLD zone inspector
|
ESC17-01455
| Aging Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 1:56:05 PM | | PASS |
|
|
Home complete and landscaped. Diamante sub BMPs to remain installed for ongoing construction.
|
ESC17-01455
| DOC - Permit Finaled | 7/8/2019 | 7/8/2019 | 7/8/2019 1:36:51 PM | P | PASS |
|
|
|
ESC17-01236
| Aging Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 12:52:29 PM | | PASS |
|
|
No activity. Lot is vegetated. ESC permit sing posted.
|
ESC19-00621
| General Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 12:47:35 PM | P | PASS |
|
|
Storm drains in subdivision has sediment protection. Concrete washout pan onsite for homes. Builder is North Star Homes
No violations observed. WIP on multiple SFHs on Cranberry
|
ESC18-01053
| General Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 12:45:16 PM | P | PASS |
|
|
Subdivision development/infrastucture complete. New SFHs now in progress on Cranberry. BMPs installed. No corrections requested.
|
ESC18-00301
| Random Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 12:15:36 PM | P | PASS |
|
|
No activity. No issues/violations observed. SWPPP box is up
|
ESC19-00376
| General Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 11:47:12 AM | P | PASS |
|
|
track uitilities onsite with small crew. No trackout, BMPs installed.
Large stockpiles on west side of site. Will need to monitor for temporary stabilization/dust abatement if piles to remain inactive.
|
ESC18-00826
| Site Final | 7/5/2019 | 7/8/2019 | 7/8/2019 11:38:36 AM | A | NR |
|
|
landscaping still in progress
|
ESC16-01561
| General Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 9:56:15 AM | | CANC |
|
|
|
ESC17-00364
| Aging Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 9:54:13 AM | | CANC |
|
|
rescheduled for site final
|
ESC18-00427
| Site Preparation | 6/17/2019 | 7/8/2019 | 7/8/2019 8:20:40 AM | P | CANC |
|
|
data entry error
|