Inspections for the day of: Monday, August 14, 2017.
Number of inspections: 25
Percentage of inspections complete: 96 %
Percentage of inspections not complete: 4 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01167 General Inspection8/3/20178/7/2017 P 
ESC16-00625 General Inspection8/11/20178/14/20178/22/2017 3:37:22 PMACANC
ESC15-01288 General Inspection8/14/20178/14/20178/18/2017 2:15:17 PM CANC
ESC14-00788 Aging Inspection8/14/20178/14/20178/18/2017 2:15:10 PM CANC
ESC17-00774 General Inspection8/4/20178/14/20178/18/2017 2:14:56 PMPCANC
ESC14-01083 General Inspection8/14/20178/14/20178/18/2017 2:13:21 PM CANC
ESC16-00353 General Inspection8/11/20178/14/20178/18/2017 1:45:06 PMAPEND
WIP on one SFH, subdivision BMPs installed. No violations or issues observed.

Still working on the placement of backfill at top of Ridgeline and the eroded gully there.
ESC16-00853 General Inspection8/14/20178/14/20178/17/2017 12:59:46 PM CANC
ESC16-01227 Site Final8/14/20178/14/20178/17/2017 12:52:24 PMPPASS
Project complete. No ESC issues
ESC16-01100 General Inspection8/14/20178/14/20178/17/2017 11:39:10 AM PASS
Ramp is complete. Area stabilized and cleaned up. ESC permit finaled.
ESC16-00305 Aging Inspection8/14/20178/14/20178/16/2017 9:06:30 AM PASS
ESC16-00438 Aging Inspection8/14/20178/14/20178/16/2017 9:05:45 AM CANC
ESC16-01311 General Inspection8/14/20178/14/20178/16/2017 9:05:30 AM DEFR
can be finaled with BLD permit
ESC16-01600 General Inspection8/14/20178/14/20178/16/2017 9:04:18 AM CANC
see main site permit ESC16-01189
ESC16-01533 General Inspection8/14/20178/14/20178/16/2017 9:04:06 AM CANC
ESC16-00115 Aging Inspection8/14/20178/14/20178/16/2017 9:03:59 AM CANC
ESC15-00863 Aging Inspection8/14/20178/14/20178/16/2017 9:02:54 AM CANC
ESC16-01432 BMP Violation8/14/20178/14/20178/16/2017 8:59:04 AMAFAIL
Corrections needed at to projects by Wood River:

- Storm drains next to projects need DI bag maintenance
- provide trash pick up and containment on the site 1702 Mockbee
- RP agreed that they will stabilize adajacent lot and install down slope sediment controls from area that was disturbed and has backfill placed on it.

Corrections issued Monday 8/14. Follow up Friday 8/18
ESC17-00241 Site Final8/11/20178/14/20178/16/2017 8:49:46 AMPPASS
Project is complete, BMPs removed. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
ESC17-00231 Site Final8/11/20178/14/20178/16/2017 8:49:29 AMPPASS
Project is complete, BMP removed. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
ESC17-00971 Site Preparation8/4/20178/14/20178/16/2017 8:49:10 AMACANC
ESC16-00938 General Inspection8/14/20178/14/20178/14/2017 2:25:05 PM CANC
ESC16-01457 General Inspection8/14/20178/14/20178/14/2017 2:24:56 PM PEND
ESC16-01397 DOC - Permit Finaled8/14/20178/14/20178/14/2017 11:33:38 AMPPASS
ESC16-01274 DOC - Permit Finaled8/14/20178/14/20178/14/2017 11:03:27 AMPPASS