Inspections for the day of: Wednesday, August 21, 2019.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-01447 Conference8/21/20198/21/20198/29/2019 2:15:27 PMPDONE
Update permit for new contractor

New contractor did not notify ESC division they would be taking over site.

Berlum Construction RPs have been added to permit. Permit transfer has been assessed, $52.50


ESC19-00077 General Inspection8/21/20198/21/20198/26/2019 3:07:30 PMPCANC
ESC19-00201 Random Inspection8/20/20198/21/20198/23/2019 3:00:29 PMAPASS
check site...no washout onsite//near canal//

No dumped washout observed at site. No correction requests at this time.
ESC19-00304 Tracking Control8/19/20198/21/20198/23/2019 2:40:28 PMPPART
Dust control seems to have improved, with more circulation on the haul routes. Construction entrance was extended and roughened.

Shoulder along Lake Hazel needs sweeping. Request for Knife River to get sweeeper since much of the track out is from water truck moving between Baserri sub and Barnwood.
ESC18-00900 Tracking Control8/21/20198/21/20198/23/2019 2:38:02 PMPPART
Construction entrance was maintained, but there is a lot of loose sand, sediment, and gravel in the shoulder along the Lake Hazel frontage of the site.

Request to have shoulder swept next week. Much of it is from Knife River water truck going between Barnwood (trilogy) and Baserri (hayden homes).
ESC18-00899 Aging Inspection8/21/20198/21/20198/23/2019 2:15:42 PM CANC
ESC19-00574 Site Preparation8/21/20198/21/20198/23/2019 8:48:40 AMPPASS
Dustin with McAlvain 9 AM

Site walk through and SWPPP/ESC plan inspection. Project has completed tree clearing around the Willow Lane Pond and has began setting up the dewatering plan BMPs. RP to notify Boise ESC when dewatering will begin. Reviewed turbidity testing requirements. Water will discharge into a lined 3 chamber retention area and then discharge in the will lane pond, which has an outfall to the Boise River.

There is no activity or access on the east side of site, where the job trailer and construction entrance will be located. Currently office is at the Lander Street office, using the existing asphalt for construciton access. Storm drain at south end of Lander has a sediment filter bag installed.

Other BMPs include:
- concrete washout pan was used for fence post installation.
- sediment control wattles have been installed around section of the pond and in between the project area and Greenbelt.
- water truck stationed on site for dust control as needed.
- New pond perimeter access route was excavated/constructed, area on shoreline is contained by a turbidity curtain.

BMPs installed, SWPPP binder and site map are up to date with completed inspections and grading/stabilization log.

Approved.

Correciton request to post construction project sign(s) at entrance with the Boise ESC permit posted and the SWPPP/CGP 2017 permit posted.
ESC19-00114 General Inspection8/21/20198/21/20198/21/2019 3:28:58 PMPPASS
James- inspection for cleaned up Phone #: ###-####

Spilled material cleaned up. Addition perimeter BMPs installed as requested. No new corrections.

Site is back in compliance, parcel hold removed, re-inspection fee paid.
ESC19-00966 Site Preparation8/21/20198/21/20198/21/2019 2:06:25 PMPPASS
Rock wall installed. No trackout. Will need to repair wattles that were driven over by accessing from from Broadstone
ESC18-00311 General Inspection8/21/20198/21/20198/21/2019 1:57:46 PM PASS
WIP. Home near completion, not yet landscaped. No corrections needed.
ESC19-00927 Site Preparation8/21/20198/21/20198/21/2019 1:53:25 PMPPASS
Tommy ###-####

Permit posted, RP and developer on site. Much of the existing vegetation is supposed to remain, with only .6 acres of disturbed area. Perimeter wattles have been installed along Highland View. Construction entrance rock installed for truck loads. Exisitng asphalt driveway is to remain for this first phase, request that some gutter check bags be installed to treat driveway runoff.

Approved for construction.
ESC18-01016 Aging Inspection8/21/20198/21/20198/21/2019 12:33:24 PM PASS
ESC18-01016 DOC - Permit Finaled8/21/20198/21/20198/21/2019 12:33:09 PMPPASS
GRD18-00065 GRD-Final8/20/20198/21/20198/21/2019 10:57:46 AMACANC
Please call before arrival so that I can meet at Esther Simplot Park (rear parking lot). Construction is complete so I will need 10 min lead time, if possible. Thank you! Phone #: ###-#### >> Inspection requested via web by Tyler Ross Inspection cancelled from web by: Tyler Ross
ESC19-00266 DOC - Permit Finaled8/21/20198/21/20198/21/2019 8:31:52 AMPPASS
ESC18-01196 Aging Inspection8/21/20198/21/20198/21/2019 8:25:24 AM CANC
rescheduled for site final
ESC18-01187 Aging Inspection8/21/20198/21/20198/21/2019 8:24:22 AM DEFR
finaled by BLD inspector in June
ESC18-01187 DOC - Permit Finaled8/21/20198/21/20198/21/2019 8:24:06 AMPPASS
ESC18-01375 General Inspection8/21/20198/21/20198/21/2019 8:23:48 AM CANC
rescheduled for site final