ESC13-01215
| Aging Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 4:31:37 PM | | CANC |
|
|
Rescheduled for Monday 8/25
|
ESC14-00335
| General Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 4:01:28 PM | | PASS |
|
|
New covered storage structure is in progress. Water truck on site for dust control and compaction purposes. No MS4 or surface water in vicinity. Permit posted on fence. No corrections required.
|
ESC14-00657
| Site Preparation | 8/22/2014 | 8/22/2014 | 8/22/2014 3:47:10 PM | P | PASS |
|
|
Site preparation for River Heights #6. Inspection requested by Brighton Corp. RP Daniel.
Met RP on site to review SWPPP and ESC site map. BMPs for the first phase (rough grading) are installed. The construction entrance will be installed next week once the rough grading begins by Nampa Paving.
Sheet flow from upper end of development flows toward existing. A wattle has been lined against the wood fence that has been installed.
Permit and NOI posted.
Approved. Construction will begin next week once GRD permit is released.
|
ESC13-00522
| General Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 2:15:28 PM | | PASS |
|
|
Townhome frame is up, no stucco or siding yet. Permit is posted, trash and materials are contained and no trackout or illicit discharges observed. Approved.
|
ESC13-01279
| BMP Violation | 8/22/2014 | 8/22/2014 | 8/22/2014 2:09:04 PM | P | PEND |
|
|
Correction notice issued to sweep and shovel collected sediment and rocks from Lucky Harris at 11:30 AM. Scheduled onsite meeting with RP Chad Hamel at 1:30 PM.
Between the time of CN and meeting, Chad had Brown Construction laborers come and shovel the gutters and run their onsite sweeper (no vacuum). To follwo up Curtis Clean Sweep will be coming this afternoon with a vacuum for a deeper clean.
Beginning of next week Schmidt will turn over/scarify exisitng rock entrance which has filled in.
Response and corrective actions were prompt after initial requests this week were unfulfilled.
Will check conditions on Monday.
|
ESC13-00684
| General Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 11:56:58 AM | | PASS |
|
|
No activity. No corrections required at Antelope Springs at this time. Site is well contained and banks are stabilizing around Walling Creek.
|
ESC14-00657
| Site Preparation | 8/22/2014 | 8/22/2014 | 8/22/2014 11:45:19 AM | P | CANC |
|
|
Check for BMP installation. Review SWPPP on site.
|
ESC13-01157
| Aging Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 11:45:00 AM | | PASS |
|
|
Finaled.
|
ESC13-01157
| DOC - Permit Finaled | 8/22/2014 | 8/22/2014 | 8/22/2014 11:44:47 AM | P | PASS |
|
|
Home complete, landscaped, ESC conditions satisfied. All permits finaled.
|
ESC14-00788
| Site Preparation | 8/21/2014 | 8/22/2014 | 8/22/2014 11:39:21 AM | A | PART |
|
|
Check for proper BMP installation at Privada sub site. Inspection requested by Syman Co.
Silt fence perimeter is installed as indicated on ESC site map. Some areas of fence are tucked and trenched improperly - Syman will reinspect and fix as necessary.
SWPPP and permit are onsite. Advised RP Lance to make sure inspection forms and corrective action forms are available in the SWPPP binder onsite.
|
ESC14-00680
| Site Preparation | 8/21/2014 | 8/22/2014 | 8/22/2014 10:10:40 AM | A | PASS |
|
|
Brett Phone #: ###-####
Permit posted, construction is to start this afternoon. Flat site with homes on both adjacent lots. BMPs include daily housekeeping and downstream drop inlets.
Requested that all inlets in Trailside Place be maintained next week. RP Brett agreed.
|
ESC14-00492
| Random Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 10:06:22 AM | P | PART |
|
|
Home is near completion and awaiting landscaping and interior work.
2 corrections:
1. Drop inlet filter bag downstream at corner of Cruzette & Jump Creek has been damaged and needs replacement and maintenance.
2. Sweep gutter and sidewalk in front of home and down towards Jump Creek.
Verbal correction notice issued to CBH RP Brett.
|
ESC13-00187
| Aging Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 9:36:22 AM | | PASS |
|
|
Not yet landscaped/stabilized. No sediment runoff. BLD already finaled, will wait till stabilization is acheived.
|
ESC14-00349
| General Inspection | 8/22/2014 | 8/22/2014 | 8/22/2014 9:00:09 AM | | PASS |
|
|
WIP. Phillipi is under construction so is currently dirt. Minimal trackout to Irving. No other violations observed. Work is contained well with the Simplot Plant Science complex.
|