Inspections for the day of: Wednesday, August 31, 2016.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00288 General Inspection8/30/20168/31/20169/2/2016 10:18:27 AMPPASS
Sidewalk, street and gutter have been swept clean. Perimeter wattles re-installed. No trackout or discharges observed. Permit sign posted.

Site is back in compliance, approved.
ESC16-00966 General Inspection8/31/20168/31/20168/31/2016 4:33:26 PMPPEND
report of excessive dust coming off large stockpile...

Informed RP of issue. Called with update from field.

Excavator now in process of removing stockpile. Any remaining backfill that is in a windy location may be moved to the adjacent parcel, which is owned by Canyon Crest.

Will verify corrections tomorrow.
ESC15-01078 Site Final8/2/20168/31/20168/31/2016 3:19:15 PMPFAIL
Final warning to remove DI bag in storm drain on Old Sport. No other violations occuring. Multiple requests already issued to CBH.
ESC16-00216 Site Preparation8/31/20168/31/20168/31/2016 1:13:10 PMPPASS
Clint Phone #: ###-####

BMPs installed; permit posted. Active projects in compliance. Approved.
ESC16-00185 Aging Inspection8/31/20168/31/20168/31/2016 12:13:48 PM PASS
WIP on frame. No discharge or spills from site. No trackout. Subdivision BMPs installed.
ESC16-00425 DOC - Permit Finaled8/31/20168/31/20168/31/2016 12:10:37 PMPPASS
Home construciton complete. Site is landscaped and stabilized. No other corrections or actions needed. Permit finaled.
ESC16-00425 DOC - Permit Finaled8/31/20168/31/20168/31/2016 12:09:33 PMPPASS
Home complete and landscaped. Sidewalk and street in front of home cleaned. DI bag to remain installed during active construction on street.
ESC16-00232 DOC - Permit Finaled8/31/20168/31/20168/31/2016 12:07:18 PMPPASS
Home complete and landscaped. No temp. BMP removal required due to active SFHs in RH#6. Conditions satisfied.
ESC16-00390 Site Final8/15/20168/31/20168/31/2016 12:01:08 PMANR
rescheduled
ESC16-01117 Site Preparation8/31/20168/31/20168/31/2016 11:58:03 AMPPASS
Clint Phone #: ###-####


Permit sign posted. First new units of new DHE phase #14. Inlets have protection. Concrete washout to be constructed prior to foundation
ESC16-01120 Site Preparation8/31/20168/31/20168/31/2016 11:57:41 AMPPASS
Clint Phone #: ###-####

Permit sign posted. First new units of new DHE phase #14. Inlets have protection. Concrete washout to be constructed prior to foundation
ESC14-01083 General Inspection8/31/20168/31/20168/31/2016 11:50:22 AM PART
Park Place sub in progress. No development or infrastructure work remaining. Onsite inlets have filter bags installed. Individual units are permitted/inspected seperately. No trackout or fugitive dust. Large portable washout for cement trucks is located across the BV Drive.

RP for Brighton Homes to build a new onsite liquid washout for wall-board and paint. I also requested these sub-contractors be warned about washing out on driveways and gutters.

Correction issued to Brighton Homes regarding wall board material being washed out in gutter near stormdrain. Inlet bag to be replaced, material swept up, and training with culprit performed.
ESC16-00148 BMP Violation8/31/20168/31/20168/31/2016 11:35:31 AMAFAIL
Wallboard material and/or plaster material washout in gutter next storm drain within Park Place. DI filter bag full of solidfied material. Need to change out before end of the day. Will check back tomorrow AM.

Verbal CN issued to Erbie w/ Brighton
ESC16-01060 Site Preparation8/31/20168/31/20168/31/2016 11:17:29 AMAPASS
Inspection requested via web by Erby Gonzales



4 new units starting in the recently complete phase of Barber Valley townhomes. Permit sign posted. Concrete washout containment is onsite, and storm drains have sediment filter protection. Approved.
ESC16-01058 Site Preparation8/31/20168/31/20168/31/2016 11:17:16 AMAPASS
Inspection requested via web by Erby Gonzales



4 new units starting in the recently complete phase of Barber Valley townhomes. Permit sign posted. Concrete washout containment is onsite, and storm drains have sediment filter protection. Approved.
ESC16-01059 Site Preparation8/31/20168/31/20168/31/2016 11:17:00 AMAPASS
Inspection requested via web by Erby Gonzales



4 new units starting in the recently complete phase of Barber Valley townhomes. Permit sign posted. Concrete washout containment is onsite, and storm drains have sediment filter protection. Approved.
ESC16-01055 Site Preparation8/31/20168/31/20168/31/2016 11:16:46 AMAPASS
Inspection requested via web by Erby Gonzales

4 new units starting in the recently complete phase of Barber Valley townhomes. Permit sign posted. Concrete washout containment is onsite, and storm drains have sediment filter protection. Approved.
ESC15-01391 General Inspection8/31/20168/31/20168/31/2016 10:23:41 AM PASS
WIP on private estate poolhouse. No violations observed.
ESC15-01569 Aging Inspection8/31/20168/31/20168/31/2016 8:56:47 AM PASS