ESC18-00311
| General Inspection | 8/6/2019 | 8/6/2019 | 8/13/2019 3:44:32 PM | | CANC |
|
|
|
ESC17-00954
| General Inspection | 8/6/2019 | 8/6/2019 | 8/13/2019 3:43:25 PM | | CANC |
|
|
|
ESC19-00779
| Site Preparation | 8/5/2019 | 8/6/2019 | 8/8/2019 10:38:32 AM | P | CANC |
|
|
rescheduled
|
ESC18-00363
| General Inspection | 8/6/2019 | 8/6/2019 | 8/7/2019 4:41:11 PM | | PASS |
|
|
|
ESC18-00940
| Site Final | 8/1/2019 | 8/6/2019 | 8/7/2019 11:47:25 AM | P | PASS |
|
|
|
ESC17-01488
| General Inspection | 8/1/2019 | 8/6/2019 | 8/7/2019 11:47:16 AM | P | PASS |
|
|
No new activity. Building appears to be vacant. Will check for site final next inspection
|
ESC18-01206
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:46:06 AM | A | PASS |
|
|
9 AM Micron Campus inspection
Project complete, no ESC requests
|
ESC18-00616
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:45:36 AM | A | PASS |
|
|
9 AM Micron Campus inspection
- updated SWPPP binders and site maps; weekly site inspections; permit info posted - designated construction access route and track-out control - storm drain inlet protection on all receiving inlets. Stormwater is retained onsite at Micron. - large capacity lined concrete washout containment pit - covered trash dumpsters/material separation - containers for material and equipment storage prevent exposure to rain - spill kits located in various locations around site. - water trucks on duty to keep down dust.
No violations observed. Site is clean, BMPs are installed correctly, SWPPP record keeping is satisfactory. No correction requests at this time, Micron projects are currently in compliance.
|
ESC18-00251
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:45:18 AM | A | PASS |
|
|
9 AM Micron Campus inspection
- updated SWPPP binders and site maps; weekly site inspections; permit info posted - designated construction access route and track-out control - storm drain inlet protection on all receiving inlets. Stormwater is retained onsite at Micron. - large capacity lined concrete washout containment pit - covered trash dumpsters/material separation - containers for material and equipment storage prevent exposure to rain - spill kits located in various locations around site. - water trucks on duty to keep down dust.
No violations observed. Site is clean, BMPs are installed correctly, SWPPP record keeping is satisfactory. No correction requests at this time, Micron projects are currently in compliance.
|
ESC19-00911
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:44:58 AM | A | PASS |
|
|
9 AM Micron Campus inspection
|
ESC18-00006
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:44:41 AM | A | CANC |
|
|
9 AM Micron Campus inspection
see site final
|
ESC16-00242
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:43:52 AM | A | CANC |
|
|
9 AM Micron Campus inspection
see site final
|
ESC18-01005
| General Inspection | 7/24/2019 | 8/6/2019 | 8/7/2019 11:42:23 AM | A | PASS |
|
|
9 AM Micron Campus inspection
see also detailed Micron Inspection report for August 6, 2019.
- updated SWPPP binders and site maps; weekly site inspections; permit info posted - designated construction access route and track-out control - storm drain inlet protection on all receiving inlets. Stormwater is retained onsite at Micron. - large capacity lined concrete washout containment pit - covered trash dumpsters/material separation - containers for material and equipment storage prevent exposure to rain - spill kits located in various locations around site. - water trucks on duty to keep down dust.
No violations observed. Site is clean, BMPs are installed correctly, SWPPP record keeping is satisfactory. No correction requests at this time, Micron projects are currently in compliance.
Walkway project still open
|
ESC18-01121
| General Inspection | 8/6/2019 | 8/6/2019 | 8/7/2019 9:39:11 AM | | PEND |
|
|
|
ESC17-01484
| Aging Inspection | 8/6/2019 | 8/6/2019 | 8/7/2019 8:26:19 AM | | CANC |
|
|
|
ESC16-01278
| General Inspection | 8/6/2019 | 8/6/2019 | 8/7/2019 8:25:22 AM | | CANC |
|
|
rescheduled for site final
|
ESC17-01111
| Aging Inspection | 8/6/2019 | 8/6/2019 | 8/7/2019 8:23:20 AM | | CANC |
|
|
|
ESC19-00839
| General Inspection | 7/23/2019 | 8/6/2019 | 8/5/2019 10:52:20 AM | A | PASS |
|
|
Grading and infrastructure in progress. No trackout. Permit posted.
Fugitive dust control water truck doing a good job keeping dust down.
|