ESC17-00984
| Aging Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 4:45:14 PM | | PASS |
|
|
WIP on detached garage. Frame is up. No ESC issues.
|
ESC18-00225
| Site Final | 9/10/2018 | 9/10/2018 | 9/10/2018 4:17:42 PM | P | PASS |
|
|
Home complete and landscaped. ESC permit conditions for home are satisfied, see ESC18-00020 for all remaining ESC BMP removal. This permit finaled.
|
ESC17-01713
| Site Final | 9/10/2018 | 9/10/2018 | 9/10/2018 4:16:59 PM | P | PASS |
|
|
Home complete and landscaped. ESC permit conditions for home are satisfied, see ESC18-00020 for all remaining ESC BMP removal. This permit finaled.
|
ESC18-00048
| Site Final | 9/10/2018 | 9/10/2018 | 9/10/2018 4:14:32 PM | P | PASS |
|
|
Home complete and landscaped. ESC permit conditions for home are satisfied, see ESC18-00020 for all remaining ESC BMP removal. This permit finaled.
|
ESC17-01715
| Site Final | 9/10/2018 | 9/10/2018 | 9/10/2018 4:10:33 PM | P | PASS |
|
|
Home complete, landscaped, cleaned, and listed for sale. Temp BMPs on street and surrounding areas covered by main HRN permit, see ESC18-00020
|
ESC18-00084
| Site Final | 9/10/2018 | 9/10/2018 | 9/10/2018 4:08:31 PM | P | NR |
|
|
Need to pick up discarded wattles and silt fence post around the home site before final. HOme is complete, landscaped & occupied.
|
ESC18-00629
| Random Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 4:05:38 PM | P | PASS |
|
|
|
ESC18-00495
| General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 4:05:03 PM | P | PASS |
|
|
|
ESC18-00892
| General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 3:39:35 PM | P | PASS |
|
|
Framing in progress. Trash contained, permit posted. No discharges.
Area behind fence used for access may require revegetation upon completion of homes along Millbrook
|
ESC14-01083
| Site Final | 9/10/2018 | 9/10/2018 | 9/10/2018 3:25:53 PM | P | PASS |
|
|
All streets and gutters have been swept clean. Debris captured by flaps of storm drian bags & grates has been removed. All temporary storm drain protection has been removed. All areas disturbed are now stabilized and landscaped. Phase 1 & 2 of Park Place Townhomes are complete, this ESC permit finaled. Stockpile to the west of site is covered by ESC16-01650.
|
ESC17-00618
| General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 11:53:03 AM | | PASS |
|
|
WIP on exterior finish. Storm drains still have sediment bags installed. These will need to be removed in order to get ESC site final approval.
No violations observed.
|
ESC18-00180
| General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 11:49:16 AM | P | PEND |
|
|
WIP on road improvements and joint trench on Ash Street. Road closed to one lane. Receiving storm drain has sediment filter bag installed. No spills or leaks observed. Sweepers tracks on River Street are signs of clean up.
Follow up inspection scheduled for clean up of stockpiles and loose dirt in roadway
|
ESC17-01687
| General Inspection | 9/10/2018 | 9/10/2018 | 9/10/2018 11:48:40 AM | P | PEND |
|
|
WIP on road improvements and joint trench on Ash Street. Road closed to one lane. Receiving storm drain has sediment filter bag installed. No spills or leaks observed. Sweepers tracks on River Street are signs of clean up.
Follow up inspection scheduled. See main site development permit for ESC, ESC18-00180.
|