ESC13-00449
| Tracking Control | 9/11/2014 | 9/11/2014 | 9/11/2014 4:38:46 PM | P | PART |
|
|
Check to see that road has been swept towards end of the day. Hauling in dirt and using water for compaction and dust so there is trackout despite the vehicle tracking pad.
Sweeper tractor onsite but not in use. Still significant trackout. Rock entrance is not working. Going to meet with RP Herb tomorrow to figure out how to reduce trackout.
|
ESC14-00422
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 4:25:42 PM | | PASS |
|
|
Project complete. ESC conditions satisfied. Disturbed area has been stabilized.
|
ESC14-00422
| DOC - Permit Finaled | 9/11/2014 | 9/11/2014 | 9/11/2014 4:25:15 PM | P | PASS |
|
|
|
ESC12-00130
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 3:56:22 PM | | PASS |
|
|
River Heights is in progress. Silt fence and greenbelt barrier are in good protection, no sediment leaving site on the river side.
There is no curbing yet hard surface so the street margins have some sediment under the security fence. Will need to request sweeping next inspection.
No fugitive dust or trackout. No corrections at this time.
|
ESC14-00085
| Aging Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 12:00:10 PM | | PASS |
|
|
Monument sign and construction activity at Adams School is complete. ESC conditions satisfied.
|
ESC14-00085
| DOC - Permit Finaled | 9/11/2014 | 9/11/2014 | 9/11/2014 11:58:15 AM | P | PASS |
|
|
|
ESC14-00081
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:41:43 AM | | PASS |
|
|
No correcctions at site. Culdesace is clean, permiter vegetative barrier has been maintained through duration of project. Trash and materials are contained. Approved.
|
ESC13-01046
| Aging Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:30:27 AM | | PART |
|
|
No violations specificilly at house but re-requested that drop inlets at Honeycomb and Wolf Tree be installed today. Tahoe Homes' project.
|
ESC14-00657
| Random Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:21:22 AM | A | PASS |
|
|
River Heights # 6 has started with clearing and preliminary grading complete. Since starting no complaints received; no dust or trackout issues observed.
Stationary water tank is located on site; permits posted.
|
ESC13-00070
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:18:46 AM | | PASS |
|
|
Terraces condo unit in progress. No trackout to Council Springs; silt fence perimeter is intact with no breaches. No corrections.
|
ESC13-00071
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:18:31 AM | | PASS |
|
|
Terraces condo unit in progress. No trackout to Council Springs; silt fence perimeter is intact with no breaches. No corrections.
|
ESC13-00072
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:18:14 AM | | PASS |
|
|
Terraces condo unit in progress. No trackout to Council Springs; silt fence perimeter is intact with no breaches. No corrections.
|
ESC12-01066
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 11:00:53 AM | | PASS |
|
|
951 Front project is in compliance. MS4 structures have protection, perimeter control is working, and no significant amounts of sediment in gutters around site. No trackout at time of inspection. Parking lot is not yet paved. Frame is up with work ongoing inside.
|
ESC14-00036
| DOC - Permit Finaled | 9/11/2014 | 9/11/2014 | 9/11/2014 10:22:26 AM | P | PASS |
|
|
|
ESC14-00036
| General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 10:21:26 AM | | PASS |
|
|
BK west wing addition is complete. BLD permit finaled. ESC conditions satisfied, no further inspections required for this project, though there is other construction on BK campus. No violations observed.
|
ESC13-01160
| Random Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 10:09:16 AM | P | PART |
|
|
Demolition occuring. Not dust control at time of inspection....
WIP. No dust control or water supply at site at time of inspection. RP Matt and site superviso Rich of Beniton Construction stated water is supposed to be used to help control demolition dust. While on site he went and stopped subcontractors and requested water control.
SWPPP is on site in trailer. No other issues at time of inspection. Will continue to monitor.
|
ESC13-00449
| Site Preparation | 9/10/2014 | 9/11/2014 | 9/11/2014 9:40:12 AM | A | PASS |
|
|
Herb Phone #: ###-####-access is 2652 S Philippi
Meeting with Herb onsite conducted. No surface waters or MS4 structures in vicinity of site. Dirt is being hauled in currently to build the vehicle display berm.
There is significant trackout to Orchard that I requested be swept at minimum 1-2 x daily. Herb stated it was swept once earlier.
Main BMP will be trackout control and dust suppression. Permit posted. Approved.
|
ESC14-00032
| Aging Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 8:45:07 AM | | PASS |
|
|
Finaled.
|
ESC14-00032
| DOC - Permit Finaled | 9/11/2014 | 9/11/2014 | 9/11/2014 8:44:54 AM | P | PASS |
|
|
SFH project is complete and stabilized. ESC conditions satisfied.
|