MIS18-00356
| ESC-Conference | 9/11/2018 | 9/11/2018 | 9/13/2018 8:21:31 AM | A | DONE |
|
|
Stockpiles were placed as a deterrent to overnight campers frequenting the area. No material leaving site. Plans are in the making for development.
|
ESC17-01126
| Site Preparation | 9/10/2018 | 9/11/2018 | 9/11/2018 11:01:55 AM | A | PASS |
|
|
Permit posted. BMPs installed. RP ordered Site Preparation inspection.
DI bag on 15th, perimeter wattlle properly installed. WIP on placing foundation forms.
Request to have lined/leakproof concrete washout onsite or prohibit onsite washout.
|
ESC17-01491
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:46:56 AM | | PEND |
|
|
Bridge complete. No ESC corrections directly related to project.
ESC permit to remain open for a coordinated old BMP and construction related trash pick up in Walling Creek between the new bridge and Parkcenter. Partners will be Brighton Corp, Brighton Homes, Boise ESC divisision and BPR.
Date of pickup tbd, October or November.
|
ESC17-00824
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:32:16 AM | | CANC |
|
|
|
ESC17-01538
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:32:08 AM | | PEND |
|
|
Stockpiling occuring on adajacent lot 400 W Parkcenter. SWO posted on that site.
Temporary path is complete. No activity. No ESC corrections.
|
ESC17-01688
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 10:22:00 AM | | PEND |
|
|
road work and stockpiles in ROW. Dry weather, no discharges. Entrance to River is blocked off. DI protected.
Folllow up scheduled on main site permit to check on post construction clean up of loose dirt.
|
ESC18-00814
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 8:36:27 AM | P | FAIL |
|
|
Correction requested to RP Ben: - post ESC signs on ZEC sites on Harris Ranch Road - confirm washout is lined or request use of HH roll off washouts - pick up trash in between HR Road and subdivision fence and Eckert.
|
ESC17-00706
| Aging Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 8:09:48 AM | | CANC |
|
|
rescheduled for site final
|
ESC15-00857
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 8:09:34 AM | | CANC |
|
|
|
ESC17-01317
| General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 8:02:49 AM | | PASS |
|
|
Inpsected 9/10 PM. No ESC issues, home is framed and flat work poured.
|
ESC17-00898
| Aging Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 8:01:51 AM | | CANC |
|
|
|