Inspections for the day of: Thursday, September 6, 2018.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01662 General Inspection9/6/20189/6/20189/10/2018 4:45:55 PM PASS
Near completion. Need to stabilized hillside below pool house sod area and Barber Driver.
ESC18-00892 General Inspection8/17/20189/6/20189/10/2018 3:39:43 PMACANC
ESC17-00774 General Inspection9/5/20189/6/20189/10/2018 3:34:14 PMAPASS
NO new activity or recent construction. No water in Warm Springs creek except close to the River. Willows on lower section are growing well, upper section was too dry so many of the cuttings have dried out and died. No erosion, loose netting or other issues observed.
ESC17-01437 Site Final9/6/20189/6/20189/10/2018 3:08:03 PMPPASS
Work complete. Home is landscaped, stabilized, and cleaned. Temp BMPs (DI bag downhill on HV Road) will be removed under main site ESC permit.
ESC18-00069 General Inspection9/4/20189/6/20189/6/2018 1:44:11 PMAPASS
Area in front of bikelane and in crosswalks was swept up. New work occuring the west lane now. No new corrections.
ESC17-01437 General Inspection9/6/20189/6/20189/6/2018 10:23:14 AM PASS
ESC16-01650 General Inspection9/6/20189/6/20189/6/2018 9:46:21 AMAPART
WIP on SFHs. Foundations for the west section have been poured and will be ready for framing this fall & winter. Concrete washout pit located at west end of street. Bottom is lined

Slope between subdivision and greenbelt has been vegetated. Supplemental irrigation has been installed to help get grasses established.

Silt fence was removed. Bark wattles are properly installed.
Correction requests for next inspection issued to Steve with CMG:

-A final row should be installed at the toe of the slope.
- sweep up concrete slurry dribbled on path from the new subdivision access path.
- fix lining on washout (request to Blackrock Homes)
ESC18-00313 Tracking Control9/5/20189/6/20189/6/2018 9:25:37 AMAPEND
RP stated clean up has begun, construciton entrances and storm drain protection will be installed by Friday. Rescheduled.
ESC17-01200 General Inspection9/6/20189/6/20189/6/2018 8:07:54 AM CANC
ESC17-01652 General Inspection9/6/20189/6/20189/6/2018 8:07:04 AM CANC
ESC17-00078 General Inspection9/4/20189/6/20189/5/2018 12:52:46 PMPPASS
No activity. SFHs are now in planning and permitting phase. No violations observed, no requests at this time