Inspections for the day of: Friday, January 20, 2017.
Number of inspections: 15
Percentage of inspections complete: 40 %
Percentage of inspections not complete: 60 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00657 General Inspection1/16/20171/16/2017   
ESC16-00159 General Inspection1/17/20171/17/2017   
ESC15-00306 General Inspection1/18/20171/18/2017   
ESC15-00762 General Inspection1/18/20171/18/2017   
ESC16-00288 General Inspection1/18/20171/18/2017   
ESC15-01543 General Inspection1/19/20171/19/2017   
ESC13-01279 General Inspection1/20/20171/20/20171/27/2017 10:48:28 AM CANC
Road closed due to landslide and adverse winter conditions
ESC16-00435 General Inspection1/20/20171/20/20171/23/2017 4:02:15 PM DONE
See ESC15-01579
ESC15-00729 General Inspection1/20/20171/20/20171/20/2017 12:55:39 PMPPEND
Site walk through with Syman. Walked back access road to evaluate the concerns. Syman is planning on diverting the water to flow through the rip rap channel rather than cutting off to the side.

Viewed the check dams along barber dr. and Syman will work with engineer for redesign. Noted that water is flowing around check dams during high flow rather than down the center of the dam structures the cahnnel should be stabilized with ECB.
ESC16-01481 Complaint Inspection1/20/20171/20/20171/20/2017 12:16:08 PMAPASS
clogged storm drain with rock and dirt. No activity on this site. See ESC16-01420
ESC16-01420 Complaint Inspection1/20/20171/20/20171/20/2017 12:14:49 PMAPASS
complaint of clogged storm drain with rock and dirt. Track flow of stormwater to nearest stormdrain. Did not observe any dirt cloging. Appears the wood bros. may have stocked piled their driveway dirt temporarily causing a blockage. Have since filled the driveway and removed obstruction. Notified wood bro. will continue any remaining clean up as snow melts.
ESC16-01461 Site Preparation1/19/20171/20/20171/20/2017 11:41:34 AMAPASS
Colby Phone #: ###-####. Approved for construction. subdivision BMPs installed from previous projects.
ESC16-00603 General Inspection1/20/20171/20/2017   
ESC15-00142 General Inspection1/20/20171/20/2017   
ESC16-00225 General Inspection1/20/20171/20/2017