Inspections for the day of: Monday, January 23, 2017.
Number of inspections: 12
Percentage of inspections complete: 25 %
Percentage of inspections not complete: 75 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00657 General Inspection1/16/20171/16/2017   
ESC16-00159 General Inspection1/17/20171/17/2017   
ESC15-00306 General Inspection1/18/20171/18/2017   
ESC15-00762 General Inspection1/18/20171/18/2017   
ESC16-00288 General Inspection1/18/20171/18/2017   
ESC15-01543 General Inspection1/19/20171/19/2017   
ESC15-00142 General Inspection1/20/20171/20/2017   
ESC16-00225 General Inspection1/20/20171/20/2017   
ESC16-00603 General Inspection1/20/20171/20/2017   
ESC15-00729 General Inspection1/20/20171/23/20171/26/2017 12:19:21 PMPPASS
Meet with Luke (ACHD ESC) to do turbidity testing at lower outlet into creek. Samples were about 16NTU. Corrections were made to the rip rock channel where the water had run outside of the rip rock. They added a sock to the end of the outlet pipe, rewattled the slop next to the outlet, sandbagged the natural channel and some other problem areas to slow water and keep it in the channel. Very low flow occuring.

No improvment to the check dams. Looked at it with Luke (ACHD)
ESC16-00437 General Inspection1/23/20171/23/20171/23/2017 4:02:56 PM DONE
See ESC15-01579
ESC16-00436 General Inspection1/23/20171/23/20171/23/2017 4:02:35 PM DONE
See ESC15-01579