Inspections for the day of: Thursday, March 16, 2017.
Number of inspections: 22
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00935 General Inspection3/16/20173/16/20173/20/2017 11:35:46 AM PASS
WIP. BMPs okay no maintenance needed. No corrections requested. Met with RP on site and discussed planed construction timeline.
ESC16-01636 General Inspection3/9/20173/16/20173/17/2017 4:22:31 PMPFAIL
WIP on SFH.
Corrections requested. Sweep and preform concrete washout maintenance.
Left message with RP requesting corrections.
ESC16-00805 Aging Inspection3/16/20173/16/20173/17/2017 2:31:55 PM PASS
Landscaping complete. DI bag remaining on Trailwood way will have to be removed before site final. Project complete.
ESC16-00665 Aging Inspection3/16/20173/16/20173/17/2017 2:29:03 PM PASS
Landscaping complete. No trash remaining on site. Okay to final.
ESC16-00754 Aging Inspection3/16/20173/16/20173/17/2017 1:00:22 PM PASS
Demolition complete. Surroundings are fully vegetated. Okay to final.
ESC17-00012 General Inspection2/28/20173/16/20173/17/2017 11:53:51 AMPPASS
ESC16-00853 Tracking Control3/9/20173/16/20173/16/2017 4:43:09 PMPPEND
Sweeper was not available until next week. RP has sweeper scheduled for next week. okay.
ESC15-00509 General Inspection3/16/20173/16/20173/16/2017 4:10:34 PM PASS
No ESC issues. Revegetation not complete.
ESC03-01290 DOC - Permit Finaled3/16/20173/16/20173/16/2017 2:39:27 PMPPASS
Project complete
ESC16-00708 Random Inspection3/16/20173/16/20173/16/2017 2:37:55 PMPPASS
Vertical WIP. Stockpiles are contained in vegetated front yard. Project is ok. No corrections requested.
ESC16-01269 Random Inspection3/16/20173/16/20173/16/2017 2:33:40 PMPPASS
No ESC issues observed. No landscaping has been installed. WIP on driveway and in yard.
ESC17-00053 Random Inspection3/16/20173/16/20173/16/2017 2:27:49 PMPPASS
No ESC issues observed.
ESC15-00817 General Inspection3/16/20173/16/20173/16/2017 2:27:22 PM PASS
No ESC issues observed. Landscaping almost complete. Some grasses starting on backhill. Project okay.
ESC04-00591 DOC - Permit Finaled3/16/20173/16/20173/16/2017 2:15:47 PMPPASS
Project complete
ESC16-01516 Site Final3/16/20173/16/20173/16/2017 2:14:55 PMPPASS
Project finished landscaping complete. okay to final.
ESC03-01279 Site Final3/16/20173/16/20173/16/2017 2:08:49 PMPPASS
Project finished landscaping complete. okay to final.
ESC03-00988 DOC - Permit Finaled3/16/20173/16/20173/16/2017 1:23:06 PMPPASS
Project finished. Okay to final.
ESC03-00846 DOC - Permit Finaled3/16/20173/16/20173/16/2017 1:22:44 PMPPASS
Project finished. Okay to final.
ESC16-00846 Aging Inspection3/16/20173/16/20173/16/2017 1:21:33 PM PASS
Landscaping complete. Sidewalk not completed. No ESC issues observed.
ESC16-00801 Site Final3/16/20173/16/20173/16/2017 12:57:34 PMPPASS
ESC16-00801 Aging Inspection3/16/20173/16/20173/16/2017 12:57:21 PM PASS
Demolition complete. Okay to final.
ESC16-00242 General Inspection3/14/20173/16/20173/16/2017 11:54:55 AMAPASS
9:15AM-11:00AM
• Met onsite with erosion control team
• Reviewed SWPPP, weekly inspection reports, inspection maps. SWPPP is available and inspections are up to date. Weekly inspection take place around 9:00AM each Wednesday.
• Discussed site flow and measures that have been implemented to prevent trackout and dirty discharges.
• Discussed changing RP on permit to reflect current responsible person
• Requested changing area of disturbance to reflect current size of project to include the CUP building and staging areas used for active construction.
• The drainage pond’s headwall height has been increased and is no longer discharging into Five Mile Creek.
• Preformed site walk through
• Inspected roof drain, drop inlet protection, concrete washout, staging areas, construction entrance, rock filter berms
• Discussed other BMPs being implemented on site
Corrections requested:
• Preform maintenance noted during the weekly inspections. Reinstall main construction entrance, change plastic dams to filter fabric, preform maintenance on DI bags that require attention.