Inspections for the day of: Wednesday, March 22, 2017.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-01063 General Inspection3/22/20173/22/20173/27/2017 10:39:15 AM PEND
The site preparation on Goshawk requires corrections to the concrete washout and cleaning around the DIs on Goshawk and arrow villa. Left a message for developer RP (Jill Jenkins) requesting corrections to the DI bags and the concrete washout.
There are no changes to the slide area. The drainage channel is beginning to grow vegetation. There is an eroded channel through the middle of the drainage channel. There is no standing water on flat lots. DI protections are ok. Most require sweeping around the DIs due to sediment capture build up.
Corrections requested:
1.Clean sediment around DIs on Goshawk and arrow villa
2.Maintenance to concrete washout and refresh rocked entrance
3.Clean sediment around other DIs in subdivision

ESC15-01037 Aging Inspection3/22/20173/22/20173/23/2017 10:39:03 AM PASS
Project is complete. Okay to final.
ESC16-00856 Aging Inspection3/22/20173/22/20173/23/2017 7:55:55 AM PASS
ESC15-01210 General Inspection3/22/20173/22/20173/22/2017 3:27:56 PM PASS
WIP on SFHs in subdivision. No corrections requested.
ESC16-00853 Tracking Control3/16/20173/22/20173/22/2017 3:05:34 PMPPASS
WIP on SFHs in subdivision. No corrections requested.
ESC16-00953 General Inspection3/22/20173/22/20173/22/2017 2:49:01 PM PASS
WIP. No ESC issues observed.
ESC16-00353 General Inspection3/22/20173/22/20173/22/2017 2:47:58 PM PASS
Project okay. No WIP. Concrete washout has been installed.
ESC16-01431 Site Preparation3/16/20173/22/20173/22/2017 2:46:44 PMPNR
Pre-construction meeting. Reviewed plan for construction. Discussed requirement that BMPs are installed before site inspection is requested. Plan to meet onsite for the site preparation and walk through SWPPP and ESC plan. A drainage basin is to be constructed at the lowest point on the site and will be used as a sediment control method. Not cleared to start until after site preparation inspection is complete.
ESC03-00840 DOC - Permit Finaled3/22/20173/22/20173/22/2017 1:12:35 PMPPASS
Project complete
ESC03-01348 DOC - Permit Finaled3/22/20173/22/20173/22/2017 1:10:58 PMPPASS
Expired
ESC16-00499 General Inspection3/22/20173/22/20173/22/2017 1:05:17 PM PASS
No trackout. Dirt is not spilling onto sidewalk. No corrections requested. Project ok.
ESC16-00963 General Inspection3/22/20173/22/20173/22/2017 12:56:07 PM PASS
WIP. BMPs in place and maintained. No ESC issues observed.
ESC16-00478 Aging Inspection3/22/20173/22/20173/22/2017 11:03:42 AM PASS
Building is complete. Stabilization has not been achieved. Not ready to final.
ESC17-00077 General Inspection3/6/20173/22/20173/22/2017 10:58:04 AMAPASS
Very clean site. No trackout. Excavation piles are set back from sidewalk. No dirt spilling onto sidewalk. Inlet protection okay. Project looks good.
ESC16-00822 Site Preparation3/21/20173/22/20173/22/2017 10:13:46 AMAPASS
Flat site. Spoke with RP will install construction entrance and hang sign before work begins. Okay to start.
ESC17-00115 Site Preparation3/21/20173/22/20173/22/2017 9:57:46 AMAPASS
Silt fence installed along back of site. Wattle along front perimeter. Sign is posted. Community washout located nearby. DI bag on hootowl and barber dr required maintenance. Met with RP onsite and he plans to contact Syman to clean DI bags.
ESC16-00842 Aging Inspection3/22/20173/22/20173/22/2017 9:35:31 AM PASS
No ESC issues
ESC16-01213 General Inspection3/17/20173/22/20173/21/2017 11:56:20 AMPFAIL
Trackout. Scheduled a tracking control inspection for next week.