Inspections for the day of: Tuesday, March 28, 2017.
Number of inspections: 22
Percentage of inspections complete: 95 %
Percentage of inspections not complete: 5 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00427 General Inspection3/28/20173/28/20173/28/2017 4:34:40 PM PASS
Vegetation not at 70% cover yet.
ESC16-00519 Site Final3/28/20173/28/20173/28/2017 3:59:23 PMPPASS
Work complete. Soil stable. Okay to final.
ESC16-00519 Aging Inspection3/28/20173/28/20173/28/2017 3:59:06 PM PASS
Work complete. Soil stable. Okay to final.
ESC14-01083 General Inspection3/28/20173/28/20173/28/2017 3:18:27 PM PASS
DI bags ok. No trackout. Project is clean. No corrections requested.
ESC14-00989 Site Final3/28/20173/28/20173/28/2017 2:24:11 PMPPASS
ESC14-00989 General Inspection3/28/20173/28/20173/28/2017 2:24:01 PM PASS
Work complete. Soil stable. Okay to final.
ESC16-00781 Site Final3/28/20173/28/20173/28/2017 2:23:02 PMPPASS
Work complete. Soil stable. Okay to final.
ESC16-00798 Site Final3/28/20173/28/20173/28/2017 2:22:50 PMPPASS
Work complete. Soil stable. Okay to final.
ESC16-00798 Site Final3/28/20173/28/20173/28/2017 2:22:36 PMPPASS
Work complete. Soil stable. Okay to final.
ESC16-00765 Site Final3/28/20173/28/20173/28/2017 2:22:24 PMPPASS
ESC16-00765 Aging Inspection3/28/20173/28/20173/28/2017 2:22:12 PM PASS
Work complete. Soil stable. Okay to final.
ESC16-00766 Site Final3/28/20173/28/20173/28/2017 2:21:40 PMPPASS
ESC16-00766 Aging Inspection3/28/20173/28/20173/28/2017 2:21:25 PM PASS
Work complete. Soil stable. Okay to final.
ESC16-00489 General Inspection3/28/20173/28/20173/28/2017 2:20:29 PM PASS
WIP on SFH. Minimal trackout. Subdivision BMPs ok. No corrections requested.
ESC17-00334 Site Preparation3/27/20173/28/20173/28/2017 1:41:31 PMAPASS
Sign posted and Di protection installed. Wattle is installed along a section of the backyard to prevent runoff to penitentiary creek. Okay to start.

ESC16-00723 General Inspection3/28/20173/28/20173/28/2017 11:23:11 AM PASS
Vertical WIP. No trackout. Sediment contained on site. Perimeter controls ok. No corrections requested.
ESC16-00625 General Inspection3/28/20173/28/20173/28/2017 11:06:22 AM PASS
No trackout. Silt fence ok. No corrections requested.
ESC16-01582 General Inspection3/15/20173/28/20173/28/2017 10:40:38 AMPPASS
WIP on curbs and gutters. No significant trackout. Project ok.
ESC16-00948 General Inspection3/15/20173/28/20173/28/2017 10:40:09 AMPPASS
WIP on foundations. Some trackout on interior roads. DI protection ok. No correction requested.
ESC17-00333 Site Preparation3/27/20173/28/20173/28/2017 10:39:15 AMAPASS
Meet with Homeowner. Okay to start. Very minimal to no earthwork expected. Has sign will post when project begins.
ESC16-01431 Site Preparation3/27/20173/28/20173/28/2017 10:38:40 AMAPEND
Silt fence installed. DI protection installed. install Need to post sign and construction entrance. Talked with RP and Zack onsite about requests.
ESC16-01213 Tracking Control3/21/20173/28/2017 P