Inspections for the day of: Thursday, March 9, 2017.
Number of inspections: 24
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01401 General Inspection3/9/20173/9/20173/10/2017 12:25:04 PMPPASS
DI protection installed. Wattles installed along perimeter. Some track out onto street. Trash almost full.
ESC17-00018 General Inspection3/9/20173/9/20173/9/2017 4:55:21 PMPPASS
Dewatering operation complete for current phase of construction. There is sediment piled where the perforated pipe was discharging water. Clean up of sediment is currently underway. Check back for progress. There may be a need to lower pond elevation again to complete work in the pond. Ensure dewatering BMPs are properly reinstalled before pumping from pond begins.
ESC16-00742 Aging Inspection3/9/20173/9/20173/9/2017 4:36:36 PM PASS
No ESC violations observed.
ESC16-00989 General Inspection3/9/20173/9/20173/9/2017 3:43:32 PM PASS
WIP. Perimeter controls in place. No trackout.
ESC16-01431 General Inspection3/9/20173/9/20173/9/2017 3:26:55 PMPPASS
No WIP.
ESC16-00434 General Inspection3/9/20173/9/20173/9/2017 3:02:13 PM PASS
No ESC issues observed.
ESC16-00936 General Inspection3/2/20173/9/20173/9/2017 3:02:13 PMPPASS
ESC17-00078 Site Preparation3/9/20173/9/20173/9/2017 2:15:58 PMPPASS
okay to start
ESC15-00094 General Inspection3/9/20173/9/20173/9/2017 2:12:58 PM PASS
No trackout. No ESC issues.
ESC15-01091 General Inspection3/9/20173/9/20173/9/2017 2:11:31 PM PASS
No WIP
ESC17-00077 Tracking Control3/9/20173/9/20173/9/2017 12:10:52 PMPFAIL
Inlets directly under driveway not protected.
Corrections requested: clean trackout and protect inlets as soon as possible.
Left message with RP and spoke with Chad onsite about corrections. Trackout cleanup is underway. DI protection will be installed today. Will follow up tomorrow.

ESC16-01561 General Inspection3/9/20173/9/20173/9/2017 11:11:57 AMPPASS
Checked on dewatering operation. Discharge is clean. No corrections. Discharge rate has been reduced from yesterdays flow rate.
ESC15-01579 Tracking Control3/8/20173/9/20173/9/2017 11:10:22 AMPPASS
SWPPP is up to date. Trackout has been cleaned up. Small push electric sweeper is on site and used when trackout occurs. Minor corrections are noted in SWPPP and action to fix them underway. Corrections include concrete washout maintenance, slight trackout onto greenbelt, waste containers. Trash around site has been picked up.

ESC16-00437 General Inspection3/9/20173/9/20173/9/2017 11:10:22 AM PASS
SWPPP is up to date. Trackout has been cleaned up. Small push electric sweeper is on site and used when trackout occurs. Minor corrections are noted in SWPPP and action to fix them underway. Corrections include concrete washout maintenance, slight trackout onto greenbelt, waste containers. Trash around site has been picked up.

ESC16-00436 General Inspection3/9/20173/9/20173/9/2017 11:10:21 AM PASS
SWPPP is up to date. Trackout has been cleaned up. Small push electric sweeper is on site and used when trackout occurs. Minor corrections are noted in SWPPP and action to fix them underway. Corrections include concrete washout maintenance, slight trackout onto greenbelt, waste containers. Trash around site has been picked up.

ESC16-00435 General Inspection3/9/20173/9/20173/9/2017 11:10:21 AM PASS
SWPPP is up to date. Trackout has been cleaned up. Small push electric sweeper is on site and used when trackout occurs. Minor corrections are noted in SWPPP and action to fix them underway. Corrections include concrete washout maintenance, slight trackout onto greenbelt, waste containers. Trash around site has been picked up.

ESC16-01635 Site Preparation3/8/20173/9/20173/9/2017 9:50:43 AMAPASS
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
ESC16-01634 Site Preparation3/8/20173/9/20173/9/2017 9:50:28 AMAPASS
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
ESC16-01632 Site Preparation3/8/20173/9/20173/9/2017 9:50:13 AMAPASS
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
ESC16-01631 Site Preparation3/8/20173/9/20173/9/2017 9:49:58 AMAPASS
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
ESC16-01633 Site Preparation3/8/20173/9/20173/9/2017 9:49:43 AMAPASS
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
ESC16-01636 Site Preparation3/8/20173/9/20173/9/2017 9:49:30 AMAPASS
Met onsite with Kyle RP. Discussed BMP installation, trackout prevention, use of concrete washout. Okay to start. Follow up next week to ensure additional BMPs are installed. Signs are posted. Okay to start.
ESC16-00844 General Inspection3/2/20173/9/20173/8/2017 9:20:38 AMAPASS
Trackout cleaned up
ESC16-00844 General Inspection3/2/20173/9/20173/8/2017 9:20:24 AMAPASS
Trackout cleaned up