Inspections for the day of: Thursday, May 4, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00646 Aging Inspection5/4/20175/4/20175/9/2017 9:49:09 AM PASS
WIP on siding and interior. No more earth disturbing activity okay to final ESC permit.
ESC15-01138 General Inspection5/4/20175/4/20175/5/2017 12:06:36 PM PASS
Excavation on adjacent lot has begun.
ESC17-00209 Site Preparation5/4/20175/4/20175/4/2017 4:56:45 PMPPASS
Okay to start. Continue regular sweeping. Some trackout present in subdivision.

Clint Phone #: ###-####
ESC17-00206 Site Preparation5/4/20175/4/20175/4/2017 4:56:31 PMPPASS
Okay to start. Continue regular sweeping. Some trackout present in subdivision.

Clint Phone #: ###-####
ESC17-00018 General Inspection5/4/20175/4/20175/4/2017 11:06:50 AMPPEND
De-watering in progress. Water is being pumped from the surface of the stormwater ponds into the wetland to lower the pond water elevation. Water from dewatering on the east end of the project is then pumped into the storm water pond. Where there is retention time for settling.
Dewatering on the west end: The rubber filter bag was ineffective. A pond liner has been placed under the outlet pipe to prevent scour. The water sheet flowing through the wetlands into the creek on the west end and into the wetlands on the south side of the green belt. The check dams that were previously providing filtering are no longer effective due to the high waters. The main filtering method is the stormwater ponds which provide sufficient storage time to settle particiles from the dewatering on the east end of the site.
The water being discharge has low turbidity. Water entering the creek has no visible plume. The river is backing up into the wetland so no water from these discharges are reaching the river.
RP Cody continues to take turbidity measurement and sampels. The NTU readings have not exceeded regulatory limits.
Eckert Road: the water flow has decreased through the ditch on the new Eckert road since last inspection and the NTU reading have not exceeded regulatory limits

ESC17-00519 Site Preparation5/2/20175/4/20175/4/2017 9:53:18 AMANR
No construction entrance. No SWPPP sign posted.

Farewell Bend

check for construction entrance and permit posting