Inspections for the day of: Monday, June 5, 2017.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-01279 General Inspection6/5/20176/5/20176/6/2017 4:48:50 PMPPART
ECB have been staked down. No other ESC isues observed.
ESC14-00206 General Inspection6/2/20176/5/20176/6/2017 4:26:08 PMAPEND
Phase complete. Some DI bags still in place. Concrete washout needs to be cleaned up before this permit can be finaled.
ESC17-00197 Tracking Control6/2/20176/5/20176/6/2017 3:36:24 PMAPASS
WIP. Trash contained. some slight trackout. BMPs ok.
ESC16-00265 Aging Inspection6/5/20176/5/20176/6/2017 1:26:10 PM PASS
Landscaping complete okay to final.
ESC15-01579 General Inspection6/5/20176/5/20176/6/2017 10:44:03 AM PART
Fence needs repairs still
Windblown trash in pond
Continue sweeping
Dumpster ok
Site needs a trash pick up. Bottles, paint cans and other trash are littered around the site.
Talked with project manager about corrections.
Dewatering has not started yet. Project manager will call for an inspection when dewatering starts.
ESC16-00437 General Inspection6/5/20176/5/20176/6/2017 10:44:03 AM PART
Fence needs repairs still
Windblown trash in pond
Continue sweeping
Dumpster ok
Site needs a trash pick up. Bottles, paint cans and other trash are littered around the site.
Talked with project manager about corrections.
Dewatering has not started yet. Project manager will call for an inspection when dewatering starts.
ESC16-00436 General Inspection6/5/20176/5/20176/6/2017 10:44:03 AM PART
Fence needs repairs still
Windblown trash in pond
Continue sweeping
Dumpster ok
Site needs a trash pick up. Bottles, paint cans and other trash are littered around the site.
Talked with project manager about corrections.
Dewatering has not started yet. Project manager will call for an inspection when dewatering starts.
ESC16-00435 General Inspection6/5/20176/5/20176/6/2017 10:44:03 AM PART
Fence needs repairs still
Windblown trash in pond
Continue sweeping
Dumpster ok
Site needs a trash pick up. Bottles, paint cans and other trash are littered around the site.
Talked with project manager about corrections.
Dewatering has not started yet. Project manager will call for an inspection when dewatering starts.
ESC17-00610 Site Preparation6/5/20176/5/20176/5/2017 4:26:00 PMPCANC
Rescheduled.
ESC16-00435 Site Preparation6/5/20176/5/20176/5/2017 3:50:54 PMPCANC
ESC15-01391 General Inspection6/5/20176/5/20176/5/2017 9:44:06 AM CANC
ESC17-00246 General Inspection5/26/20176/5/20176/5/2017 9:42:49 AMAPASS
WIP. Vegetation is containing sediment. No trackout. Trash is contained. No corrections.
ESC15-01138 General Inspection6/5/20176/5/20176/5/2017 9:29:06 AM PART
WIP on foundation. Silt fence needs repairs. Concrete washout is being used. No trash or trackout.
ESC16-00224 Site Final6/5/20176/5/20176/5/2017 9:00:32 AMPPASS
ESC16-00224 Aging Inspection6/5/20176/5/20176/5/2017 9:00:21 AM PASS
Landscaping complete. Okay to final.
ESC16-00282 Site Final6/5/20176/5/20176/5/2017 8:59:17 AMPPASS
ESC16-00282 Aging Inspection6/5/20176/5/20176/5/2017 8:59:02 AM PASS
Landscaping complete. Okay to final.