ESC15-00731
| General Inspection | 7/17/2017 | 7/17/2017 | 7/18/2017 1:29:44 PM | | PASS |
|
|
WIP. Trash contained. silt fence ok. No trackout
|
ESC16-00989
| General Inspection | 7/14/2017 | 7/17/2017 | 7/18/2017 10:48:36 AM | A | PASS |
|
|
WIP on interior and exterior. Weeds have partially stablized the hillside. No runoff. No trackout. Trash contained. No dust issues observed.
|
ESC13-00524
| General Inspection | 7/17/2017 | 7/17/2017 | 7/18/2017 10:47:33 AM | | PEND |
|
|
Utility trenching in progress. Area where the dirt from the trenching is located needs to be swept up after the trenches are backfilled. No dust. No trackout. Trash is contained.
|
ESC15-00541
| General Inspection | 7/14/2017 | 7/17/2017 | 7/18/2017 10:45:38 AM | A | PASS |
|
|
WIP on SFHs some interior trackout. Trash contained.
|
ESC13-01273
| Aging Inspection | 7/17/2017 | 7/17/2017 | 7/18/2017 10:09:18 AM | | PASS |
|
|
Project complete. Okay to final.
|
ESC15-00729
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 4:04:25 PM | P | PASS |
|
|
WIP on main road drainage system and manholes. WIP on SFHs. Some trackout, trash is contained, no dust issues observed. No corrections requested.
|
ESC17-00540
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 3:11:58 PM | P | PASS |
|
|
|
ESC16-01733
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 3:11:46 PM | P | PASS |
|
|
Nearly ready for site final. Small area not landscaped and trash container still on site. Scheduled site final for next Monday.
|
ESC16-00914
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 3:09:44 PM | | PASS |
|
|
|
ESC17-00194
| General Inspection | 7/10/2017 | 7/17/2017 | 7/17/2017 3:09:32 PM | A | PASS |
|
|
Mixer has been removed. Trash has been picked up.
|
ESC17-00013
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 2:32:46 PM | P | PART |
|
|
Need to clean up trackout and refresh entrance/exit. Silt fence needs minor repairs.
Corrections are also noted in the SWPPP. SWPPP inspections are up to date. some stockpiles are still on site.
No WIP at time of inspections. No fugitive dust or wind blow trash.
|
ESC17-00018
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 1:57:18 PM | P | PASS |
|
|
WIP on grading for roads, creating fill dirt, and leveling stockpiles. The drainage to the East of the site along Eckert road is revegetating. Perimeter silt fence is in place and ok.
No dust control on site no fugitive dust during time of inspection. Will inform RP to have dust control ready.
No more dewatering is anticipated. The check dams and any other dewatering BMPs should be removed from the land west of the site.
No trackout and trash is contained.
|
ESC16-00822
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 1:08:10 PM | | PASS |
|
|
Interior and exterior WIP. Trash contained. No trackout. No corrections issued.
|
ESC17-00774
| Conference | 7/17/2017 | 7/17/2017 | 7/17/2017 1:06:58 PM | A | PASS |
|
|
Pre-construction meeting:
Call in site preparation inspection before work begins and after BMPs are installed ###-####
Sign will be located on old hickory by the job site trailer. The SWPPP plan is located on Old Hickory as well. Site meetings are held on Wednesdays at 9:00AM in the job trailer.
Ensure use of dust control during the stripping and excavation phase which will begin next week. Comply with all other ESC requirements for City of Boise and EPA as well.
Dewatering: Dewatering will take place. The excavator plans to strip the land first, dig test pits to determine the GW level, and then begin dewatering. The plan is to let the water sheet flow into the field across warm springs. This section of road will be closed during this time.
Call in an inspection to City of Boise before dewatering beings and after the dewatering set up is in place. This is to ensure the set up matches the approved plan and to reduce the chance of stopping the dewatering once it is underway if a change does need to be made.
Revegetation/stabilization: Will be occurring during August and September. Supplemental irrigation will be installed and used to establish the vegetation. The channel will be lined with rip rap for stabilization.
|
ESC16-01561
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 11:53:08 AM | P | PASS |
|
|
Grading is complete. curb and street are installed. No dust, no trackout, trash contained. No corrections requested.
|
ESC16-01650
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 9:50:25 AM | P | PASS |
|
|
Grading is complete. Curb and paving are complete. No dust, no trackout, trash contained. No corrections issued.
|
ESC15-00556
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 9:35:38 AM | | PASS |
|
|
WIP on SFH. Trash is contained. Streets are clean, no trackout. Concrete washout ok and in use. Signs are posted. DIs okay. No corrections requested.
|
ESC16-00936
| General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 8:04:34 AM | P | CANC |
|
|
|
ESC16-00935
| General Inspection | 7/10/2017 | 7/17/2017 | 7/17/2017 8:04:26 AM | A | CANC |
|
|
|