Inspections for the day of: Thursday, July 20, 2017.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMelissa Jannusch
TitleEROSION INSPECTOR
Phone #789-3996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00437 General Inspection7/19/20177/20/20177/20/2017 12:57:47 PMAPART
Interior trackout not cleaned or new trackout has been created. Trash is okay.
ESC16-00436 Site Preparation7/19/20177/20/20177/20/2017 12:57:40 PMAPART
Interior trackout not cleaned or new trackout has been created. Trash is okay.
ESC16-00435 General Inspection7/19/20177/20/20177/20/2017 12:57:32 PMAPART
Interior trackout not cleaned or new trackout has been created. Trash is okay.
ESC16-01409 Site Final7/20/20177/20/20177/20/2017 12:56:30 PMPPASS
ESC16-01409 Aging Inspection7/20/20177/20/20177/20/2017 12:56:22 PM PASS
Demolition complete. soil stable. No trash or trackout remaining okay to final
ESC16-01328 Aging Inspection7/20/20177/20/20177/20/2017 12:55:39 PM PASS
ESC16-01387 Site Final7/20/20177/20/20177/20/2017 11:08:11 AMPPASS
ESC16-01389 Site Final7/20/20177/20/20177/20/2017 11:08:01 AMPPASS
ESC16-01387 Aging Inspection7/20/20177/20/20177/20/2017 11:07:49 AM PASS
Project complete. Soil is stable. Okay to final.
ESC16-01389 Aging Inspection7/20/20177/20/20177/20/2017 11:07:38 AM PASS
Project complete. Soil is stable. Okay to final.
ESC16-01422 Site Final7/20/20177/20/20177/20/2017 10:47:49 AMPPASS
ESC16-01422 Aging Inspection7/20/20177/20/20177/20/2017 10:47:38 AM PASS
Project complete. No temp BMPs remaining. Okay to final
ESC17-00774 Site Preparation7/19/20177/20/20177/20/2017 10:19:15 AMAPASS
Okay to start. wattle installed. SWPPP up to date.

Jason Phone #: ###-####
ESC17-00478 General Inspection7/13/20177/20/20177/20/2017 9:32:49 AMAPASS
Trash has been maintenanced. Most bins are half full or less. Some wattles netting is still present at the entrance of subdivision. Please remove.
ESC15-01391 Site Final7/20/20177/20/20177/20/2017 8:45:23 AMPPASS
ESC15-01391 General Inspection7/20/20177/20/20177/20/2017 8:45:11 AM PASS
Project complete. Okay to final
ESC16-00948 General Inspection7/20/20177/20/20177/20/2017 8:41:04 AM CANC