Inspections for the day of: Tuesday, January 2, 2018.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01564 Aging Inspection1/2/20181/2/20181/2/2018 1:31:35 PM PASS
No disturbances along 6th street. Back yard is fenced in, nothing leaving site.
ESC17-00157 General Inspection1/2/20181/2/20181/2/2018 12:15:09 PM PASS
No new ground disturbance. Will need landscaping in spring to be finished.
ESC15-00541 General Inspection1/2/20181/2/20181/2/2018 12:08:52 PM PASS
Few vacant lots remain. No issues with runoff from melting snow.
ESC16-01559 Aging Inspection1/2/20181/2/20181/2/2018 11:37:42 AM CANC
ESC16-01559 DOC - Permit Finaled1/2/20181/2/20181/2/2018 11:37:32 AMPPASS
ESC17-00040 General Inspection1/2/20181/2/20181/2/2018 11:23:13 AM PASS
All work and disturbance contained within perimeter. No dirt leaving site. Work area is clean, work is all interior and exterior. No ground disturbing activities.
ESC17-01519 Random Inspection1/2/20181/2/20181/2/2018 10:57:44 AMPPEND
Few homesites started. Concrete was washed out onto vacant lot. No washout on site. Left message with Clint, the RP, to get it cleaned and install washout. Let him know issue with lots becoming the neighborhood dumping ground.
ESC17-01491 General Inspection1/2/20181/2/20181/2/2018 10:14:48 AMPPASS
WIP on footings. Washout on site between green belt and warm springs ave. Water leaving site is cleaner than groundwater reaching surface. Excavating and hauling away fill dirt, no trackout issues.
ESC17-00249 General Inspection1/2/20181/2/20181/2/2018 9:48:37 AM PASS
WIP on framing, interiors, and exteriors. No issues observed.
ESC17-00251 General Inspection1/2/20181/2/20181/2/2018 9:48:19 AM PASS
WIP on framing, interiors, and exteriors. No issues observed.