Inspections for the day of: Thursday, October 25, 2018.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-01292 Tracking Control10/23/201810/25/201810/31/2018 10:14:50 AMPPART
See if backfill spilloverr and trackout is cleaned up.
Backfill cleaned and street swept up. Still some dirt in gutters, street mostly clean.
ESC17-01287 General Inspection10/25/201810/25/201810/31/2018 9:39:23 AM PART
BMPs in place, wattle needs to be maintained. Needs to be trenched in.
ESC17-00513 Site Final10/25/201810/25/201810/26/2018 2:16:24 PMPPASS
ESC17-01542 Aging Inspection10/25/201810/25/201810/26/2018 11:42:09 AM PASS
Exterior work complete, no landscaping installed. Both neighboring homes are under construction.
ESC17-01783 General Inspection10/25/201810/25/201810/26/2018 11:13:37 AM FAIL
Duplex. Stucco has been washed out onto sidewalk and gutter. Site is a mess. Correction sent to listed RP.
ESC17-01414 General Inspection10/25/201810/25/201810/26/2018 11:00:46 AM FAIL
All foundations poured. Two track steers on site moving backfill. Alley behind homes is dirt covered. Old washout has been removed and dumped over the edge behind homes. Lots of assorted lose trash on ground. Inlets are protected.
ESC18-00027 General Inspection10/25/201810/25/201810/26/2018 10:51:23 AM PASS
Work completed. Wattle has been installed along perimeter of creek. Lots of wind blown trash in creek, HOA or other group needs to over creek and work on keeping it clean.
ESC17-01519 Site Final10/25/201810/25/201810/26/2018 10:17:49 AMPPASS
ESC18-01178 General Inspection10/17/201810/25/201810/26/2018 9:45:14 AMPPASS
Foundation excavated. Wattles along front, silt fence on side, rock entrance installed. Broom and shovel on site, sidewalk and street swept.
ESC17-00513 Site Final10/24/201810/25/201810/25/2018 3:42:17 PMANR
Rescheduled for 10/26. Need to see if public works wants witches hats removed from their project on fort st.
ESC18-00946 General Inspection10/25/201810/25/201810/25/2018 12:54:33 PMPPASS
Site is holding up, no ESC issues.
ESC18-01033 General Inspection10/19/201810/25/201810/25/2018 12:07:16 PMAPASS
Building is demoed, currently hauling rubble away. ater truck on site, workers spraying pile as it is being loaded to minimize dust. ESI plans on staging work and keeping parking lot in place as long as possible in order to minimize disturbed area.
ESC17-01651 Aging Inspection10/25/201810/25/201810/25/2018 11:26:06 AM CANC
ESC17-01651 DOC - Permit Finaled10/25/201810/25/201810/25/2018 11:25:59 AMPPASS
ESC16-00556 General Inspection10/25/201810/25/201810/25/2018 10:53:11 AM PASS
One homesite under construction, yard has been landscaped and is interior work only. Few poured foundations are sitting idle and overgrown. All vacant lots are week covered and stable.
ESC17-01671 Aging Inspection10/25/201810/25/201810/25/2018 10:29:20 AM CANC
ESC17-01671 DOC - Permit Finaled10/25/201810/25/201810/25/2018 10:29:12 AMPPASS