ESC19-00861
| General Inspection | 11/1/2019 | 11/1/2019 | 11/6/2019 12:50:44 PM | P | PASS |
|
|
Realigning creek started from north working sw through site. New channel is defined, more in the northern section of site. Some rock armoring has been installed on curves. Evidence of sprayed water for compaction. Strip of land grubbed parrallel to creek, most of site still has natural cover. No esc issues, work area is isolated.
|
ESC18-00900
| General Inspection | 11/1/2019 | 11/1/2019 | 11/6/2019 12:14:08 PM | P | PART |
|
|
Trucks running laps hauling fill. Some tracking aT BOTH ENTRANCES.
|
ESC18-00358
| General Inspection | 11/1/2019 | 11/1/2019 | 11/6/2019 8:39:28 AM | P | CANC |
|
|
|
ESC18-01636
| General Inspection | 11/1/2019 | 11/1/2019 | 11/4/2019 11:49:22 AM | P | PASS |
|
|
Met with Rex from Knife river while at site. They are waiting for lab results for water in pond. If it comes back clean they will pump it out into the field to the east. Contanimated dirt pile still on site, if test come back ok it will be used as fill. They are planning to pave and do curb and gutter this fall, not sure if it will get done in time. Three ponds are planned on getting built on south side of warm springs and all excavated material used for fill. Will need to set up meeting with all parties to see what plan is, nothing has any dates set yet.
|
ESC18-01626
| Site Final | 10/31/2019 | 11/1/2019 | 11/4/2019 11:07:56 AM | P | PASS |
|
|
|
ESC18-00177
| General Inspection | 11/1/2019 | 11/1/2019 | 11/4/2019 10:58:40 AM | | PASS |
|
|
WIP on both framing and foundations. Lined concrete washout on site and in use. Trash contractor on site clearing trash boxes. Site is clean in regards to trash. Lots of dirt tracked inside site, none leaving. Silt fence/ trash fence protecting creek.
|
ESC16-00625
| Site Final | 10/29/2019 | 11/1/2019 | 11/4/2019 8:27:07 AM | P | PASS |
|
|
|
ESC18-01711
| Aging Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 1:34:47 PM | | PASS |
|
|
No outside disturbances.
|
ESC18-00141
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 1:26:34 PM | | PASS |
|
|
Area clean and stable. OK to close when building permit done.
|
ESC17-00640
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 1:26:03 PM | | DONE |
|
|
|
ESC18-00844
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 11:44:33 AM | | PASS |
|
|
Lot is contained, no esc issues.
|
ESC19-00927
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 11:40:13 AM | P | PASS |
|
|
Crew on site doing horizontal boring. Boulders for wall staged on site. Nothing leaving site.
|
ESC18-00498
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 11:29:14 AM | | PASS |
|
|
Work on one home in phase. No issues, job trailer in phase.
|
ESC18-00946
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 11:20:46 AM | | PASS |
|
|
No new activity at site. Weed growth and cover. Water conveyance system still on lot, silt fence is gone.
|
ESC19-00241
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 11:14:28 AM | P | PASS |
|
|
WIP on framing. All concrete work done until spring. Plan is to have framing done and work on interior all winter. Seepage beds completed, 10" pit run all across site to have it free drain during winter. Two exits, sweeping up weekly.
|
ESC17-00190
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 10:56:47 AM | | PASS |
|
|
No new building activity.
|
ESC19-00994
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 10:56:16 AM | P | PASS |
|
|
Met with Scott on site. Is having the hillsides watered and retracked with a bigger machine, smaller machine was having issues getting up hills. Syman should start hydroseeding next week. Let him know to have wattle ends overlap and have stakes at 5' intervals.
|
ESC18-01733
| Aging Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 10:17:27 AM | | CANC |
|
|
|
ESC18-01733
| DOC - Permit Finaled | 11/1/2019 | 11/1/2019 | 11/1/2019 10:17:22 AM | P | PASS |
|
|
|
ESC17-01287
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 10:06:37 AM | | PASS |
|
|
|
ESC15-00857
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 10:02:15 AM | | PASS |
|
|
Area is clean, rp repaired silt fence at bottom. Some diirt on road at bottom from phase 10
|
ESC19-00396
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 9:46:17 AM | P | PART |
|
|
Message sent to Clint. Some trash blown into silt fence. Areas of silt fence under load and area not trenched in.
|
ESC18-01447
| General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 9:30:21 AM | P | PASS |
|
|
Hillside has been hydroseeded and tackified. Washout cleaned and ecopan now on site. Mini excavator doing rock work on perimeter of lot.
|