ESC19-01191
| Site Preparation | 11/4/2019 | 11/7/2019 | 11/13/2019 11:27:46 AM | P | PASS |
|
|
Met with PM/RP Brandon. Construction entrance leading to fenced off parking area, access road has been graveled all the way through. Delta Dental parking lot relocated, is 3/4 mix, will be responsibl;e for upkeep and trackout. Wattle has been placed around swales. Irragation ditch runs along perimeter, in plans to pipe it before irragation turned back on. Existing paved parking lot will be on site through winter. No inlets at site or on Park Center.
|
ESC18-01199
| Aging Inspection | 11/7/2019 | 11/7/2019 | 11/13/2019 9:29:01 AM | | PASS |
|
|
Landscapers on site. Home is finished.
|
ESC18-01533
| Aging Inspection | 11/7/2019 | 11/7/2019 | 11/13/2019 9:28:32 AM | | CANC |
|
|
|
ESC17-01009
| General Inspection | 11/7/2019 | 11/7/2019 | 11/8/2019 10:39:56 AM | | PASS |
|
|
Lot contained, no esc issues.
|
ESC17-00842
| General Inspection | 11/7/2019 | 11/7/2019 | 11/8/2019 10:28:00 AM | | PART |
|
|
L3 water truck parked on lower section. Talked to RP for home said someone was on site digging and doing drainage test. They had some tracking they haven't cleaned. I let hillside engineering know they were up here testing.
|
ESC19-00116
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 2:49:37 PM | | PASS |
|
|
Access from Kingston, no trackout, entrance built. Material being stored in old parking lot at entrance. Large washout on sites. Entire area surronded by pit run. Walls and roof on, lots of interior work. Workers installing seepage bed behind school.
|
ESC18-01722
| Aging Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 1:22:32 PM | | PASS |
|
|
Lot needs to be landcaped, all work on interior.
|
ESC18-01594
| Aging Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 1:10:43 PM | | CANC |
|
|
|
ESC18-01594
| DOC - Permit Finaled | 11/7/2019 | 11/7/2019 | 11/7/2019 1:10:37 PM | P | PASS |
|
|
|
ESC18-01609
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 1:10:18 PM | P | CANC |
|
|
|
ESC18-01609
| DOC - Permit Finaled | 11/7/2019 | 11/7/2019 | 11/7/2019 1:10:11 PM | P | PASS |
|
|
|
ESC18-01610
| Site Final | 11/7/2019 | 11/7/2019 | 11/7/2019 1:09:50 PM | P | PASS |
|
|
|
ESC18-01582
| Site Final | 11/7/2019 | 11/7/2019 | 11/7/2019 1:09:39 PM | P | PASS |
|
|
|
ESC18-01581
| Site Final | 11/7/2019 | 11/7/2019 | 11/7/2019 1:09:27 PM | P | PASS |
|
|
|
ESC18-01608
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 1:09:14 PM | P | PASS |
|
|
OK to final when fine paid.
|
ESC17-00315
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 12:42:06 PM | | DONE |
|
|
|
ESC19-00115
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 12:08:17 PM | | CANC |
|
|
|
ESC19-00115
| DOC - Permit Finaled | 11/7/2019 | 11/7/2019 | 11/7/2019 12:08:09 PM | P | PASS |
|
|
|
ESC17-01360
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 11:43:37 AM | | PASS |
|
|
All exterior work on phase completed. DI protections still installed. WIll final permit when RP has inlet protection removed, makes sure all trash cleaned, and does perimeter check outside area for wind blown trash.
|
ESC18-01202
| Site Final | 11/7/2019 | 11/7/2019 | 11/7/2019 11:41:57 AM | P | PASS |
|
|
|
ESC17-00519
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 11:38:22 AM | P | PASS |
|
|
Homes in multiple phases of construction. Orange fence installed on rod iron fence acting as trash catch. Inlets all have protection. Large lined washout on site and in use. Some dirt tracked on roads and sidewalks.
|
ESC19-00575
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 11:35:59 AM | P | PASS |
|
|
Home completed, backyard still needs to be landscaped.
|
ESC19-00627
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 11:35:18 AM | P | PASS |
|
|
Foundation poured, lumber on site, no work on framing.
|
ESC18-01071
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 11:26:43 AM | P | PASS |
|
|
No workers on site. Talked with neighbor while on site, were working on retention pond yestrerday on south east end. Roads, sidewalks, storm drains, and fences installed.
|
ESC19-00698
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 10:52:35 AM | P | PASS |
|
|
Curbing completed and parking lot paved, sidewalk still needs to be done. No landscaping on site. Washout on site and used. About half off building wrapped and heated for masonary and painting. No loose or blowing trash.
|
ESC19-00141
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 10:41:16 AM | P | PASS |
|
|
no site prep requested.... No ne on site. Has crushed basalt entrance, 1 lined washout, and 3 outpaks. Concrete work has begun. No loose trash or trackout.
|
ESC18-01289
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 10:26:41 AM | P | PASS |
|
|
Some of area paved and units sold. Entrance to Fed Way has been closed, concrete crew opened it. Planning on getting rest of area paved on the 15th so they don't have mud issues. Concrete washout on sites, some small trash like drinks and labels around site.
|
ESC18-00164
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 9:33:56 AM | P | FAIL |
|
|
Mountain of backfill has been idle for greater than two weeks with no temporary stabalization. No slope interupting BMPs on site. Only installed BMP is silt fence along lower perimeter. No workers at site, sewer line material staged at site.
|
ESC19-00117
| General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 8:43:35 AM | | CANC |
|
|
|
ESC19-00672
| General Inspection | 10/28/2019 | 11/7/2019 | 11/6/2019 9:14:51 AM | A | PASS |
|
|
Met with Mike the foreman at site. Will watch for mud when rain starts and clean streets as needed. I suggested a man walkway and boot brush to avoid boot track, workers parking on street throughout neighborhood. Washout is full and need to be replaced.
|