Inspections for the day of: Friday, December 13, 2019.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMichael Zawacki
TitleEROSION INSPECTOR
Phone #208-473-8333
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01479 Site Final11/29/201912/13/201912/16/2019 12:09:41 PMPPASS
WIP on last home, neighborhood bmps removed.
ESC18-01022 General Inspection12/13/201912/13/201912/13/2019 1:16:03 PMPPASS
Road paved top to bottom.
Owners of denied development were on their parcel in Jeeps. No trackout. Talked to RP about an entrance and keeping roads clean.
ESC19-00138 Aging Inspection12/13/201912/13/201912/13/2019 11:47:37 AM CANC
ESC19-00138 DOC - Permit Finaled12/13/201912/13/201912/13/2019 11:47:31 AMPPASS
ESC17-01196 DOC - Permit Finaled12/13/201912/13/201912/13/2019 11:30:52 AMPPASS
Landscaping completed.
ESC18-01002 General Inspection12/13/201912/13/201912/13/2019 11:28:34 AM PASS
Idle.
RV was moved into neighbors driveway. Wattle pallet still on site, styrofoam not cleaned.
ESC18-01717 Site Final12/13/201912/13/201912/13/2019 11:17:18 AMPPASS
ESC19-00082 BMP Violation12/11/201912/13/201912/13/2019 11:15:15 AMAPASS
Site cleaned.
ESC19-00402 Tracking Control12/13/201912/13/201912/13/2019 11:12:02 AMPFAIL
Muddy street. Home still has parcel hold.
ESC17-00791 General Inspection12/13/201912/13/201912/13/2019 10:56:42 AM PASS
No activity, no blow outs into neighbors yard.
ESC19-00371 General Inspection12/13/201912/13/201912/13/2019 10:47:49 AMPPASS
No activity at site. Lower pond has water, berm built at bottom of road to redirect flow into pond. Area is to muddy to walk.
ESC18-00488 General Inspection12/13/201912/13/201912/13/2019 10:22:57 AMPFAIL
Crew loading excavator tracked all over barnside. '
Message sent to RP.
ESC19-00024 Aging Inspection12/13/201912/13/201912/13/2019 10:12:09 AM PASS
WIP on block. No tracking. Trash crew is on site cleaning boxes. Some loose lumber scraps, no major issues.
ESC19-00023 Aging Inspection12/13/201912/13/201912/13/2019 10:11:54 AM PASS
WIP on block. No tracking. Trash crew is on site cleaning boxes. Some loose lumber scraps, no major issues.
ESC18-00177 General Inspection12/13/201912/13/201912/13/2019 10:03:41 AMPPASS
All foundations poured. Site is clean. Building work is going from west to east.
ESC18-00179 General Inspection12/13/201912/13/201912/13/2019 10:03:25 AMPPASS
All foundations poured. Site is clean. Building work is going from west to east.
ESC19-00584 General Inspection12/13/201912/13/201912/13/2019 9:59:40 AMPFAIL
Equipment is being staged on site. Construction entrances installed. Lots of stockpiled soil on south edge. No current grading activity.
Lots of trackout headed east bound from equipment deliveries and fill being brought on site.
Started running sweeper whil I was still on site.
ESC18-01636 General Inspection12/13/201912/13/201912/13/2019 9:47:29 AMPPASS
Sidewalks LLC on site working on Ped ramps and sidewalks. Crews still doing irrigation work. Some piped staged on south side of project. No dirt work.
ESC19-00245 General Inspection12/13/201912/13/201912/13/2019 9:11:58 AMPCANC
ESC18-00349 General Inspection12/13/201912/13/201912/13/2019 8:44:49 AM PASS
All current construction finished. Still has vacant lots on west end.