ESC12-00403
| General Inspection | 11/30/2017 | 11/30/2017 | | | |
|
|
|
ESC17-01493
| Site Preparation | 12/7/2017 | 12/7/2017 | 12/8/2017 11:49:21 AM | P | PASS |
|
|
Bob Phone #: ###-#### Flat lot. RP says he will keep clean and remove and regulate dumping onto lot.
|
ESC17-01530
| Site Preparation | 12/7/2017 | 12/7/2017 | 12/8/2017 11:46:22 AM | P | PASS |
|
|
Bob Phone #: ###-#### Flat lot. RP says he will keep clean and remove and regulate dumping onto lot.
|
ESC16-01232
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 3:14:31 PM | | PASS |
|
|
Landscapers installing sprinkler system. ADS installed for drainage. Concrete curing under blankets. No loose trash or dirt on site.
|
ESC13-00806
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 3:13:07 PM | | PASS |
|
|
landscapers installing sprinkler system. ADS pipe installed for drainage. Concrete currently under blankets.
|
ESC16-00935
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 12:45:03 PM | | PEND |
|
|
Area has been stabalized. Pile of gravel in road, will need to monitor to see if it is soon removed.
|
ESC16-00936
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 12:44:39 PM | | PEND |
|
|
Area has been stabalized. Pile of gravel in road, will need to monitor to see if it is soon removed.
|
ESC16-00406
| Tracking Control | 12/7/2017 | 12/7/2017 | 12/7/2017 12:18:52 PM | P | PASS |
|
|
Trackout cleaned up. Gutters have been cleaned.
|
ESC16-01187
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 12:07:51 PM | | PASS |
|
|
Taljked to George whil on site. Front yard still needs landscaping, they are working on getting bond. Rock wall completed, pad poured in back yard and some sod down.
|
ESC16-00901
| Aging Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 11:36:20 AM | | PASS |
|
|
WIP. All phases under construction, some complete. Using lot at corner of Bogart and State for storage. No trackout, trash has a dumptster. About half of project is landscaped. Most concrete work is done, there is a washout on site. Some dirt stockpiling but no issues with dust at time of inspection.
|
ESC16-00899
| Aging Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 11:36:07 AM | | PASS |
|
|
WIP. All phases under construction, some complete. Using lot at corner of Bogart and State for storage. No trackout, trash has a dumptster. About half of project is landscaped. Most concrete work is done, there is a washout on site. Some dirt stockpiling but no issues with dust at time of inspection.
|
ESC16-00898
| Aging Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 11:35:51 AM | | PASS |
|
|
WIP. All phases under construction, some complete. Using lot at corner of Bogart and State for storage. No trackout, trash has a dumptster. About half of project is landscaped. Most concrete work is done, there is a washout on site. Some dirt stockpiling but no issues with dust at time of inspection.
|
ESC16-01218
| DOC - Permit Finaled | 12/7/2017 | 12/7/2017 | 12/7/2017 11:07:46 AM | P | PASS |
|
|
|
ESC17-00170
| Aging Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 10:44:49 AM | | CANC |
|
|
|
ESC17-00170
| DOC - Permit Finaled | 12/7/2017 | 12/7/2017 | 12/7/2017 10:44:39 AM | P | PASS |
|
|
|
ESC16-01645
| Aging Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 10:14:55 AM | | CANC |
|
|
|
ESC16-01645
| DOC - Permit Finaled | 12/7/2017 | 12/7/2017 | 12/7/2017 10:14:43 AM | P | PASS |
|
|
|
ESC16-00841
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 9:54:43 AM | | CANC |
|
|
|
ESC16-00841
| DOC - Permit Finaled | 12/7/2017 | 12/7/2017 | 12/7/2017 9:54:34 AM | P | PASS |
|
|
|
ESC17-00013
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 9:39:30 AM | | PASS |
|
|
No work today, site frozen. Road paved and survey stakes in ground. Biggest mess is from geese.
|
ESC16-01560
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 9:20:54 AM | | PASS |
|
|
Currently a staging yard. No trackout leaving or trash on site.
|
ESC16-00990
| General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 9:00:30 AM | | PASS |
|
|
No WIP
|