ESC19-00616
| Aging Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 1:34:12 PM | | CANC |
|
|
|
ESC19-00616
| DOC - Permit Finaled | 2/28/2020 | 2/28/2020 | 2/28/2020 1:34:04 PM | P | PASS |
|
|
|
ESC19-00444
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 12:12:42 PM | | PASS |
|
|
Lots of workers at house, have cul de sac blocked. Will need to make sure sidewalk and street is swept.
|
ESC17-01009
| Site Final | 2/24/2020 | 2/28/2020 | 2/28/2020 11:41:43 AM | P | PASS |
|
|
|
ESC19-01110
| BMP Violation | 2/25/2020 | 2/28/2020 | 2/28/2020 11:27:34 AM | A | PASS |
|
|
Swept clean
|
ESC19-00572
| Aging Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 11:07:57 AM | | PASS |
|
|
Lot is fenced and stable, can't tell if foundation still in
|
ESC19-00542
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:58:03 AM | | PART |
|
|
Site is contained, no trackout. Some spilled washout next to eco pans. Some washout/concrete on site, looks like where they transfered to pump truck. Should be cleaned.
|
ESC19-00093
| Aging Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:42:23 AM | | PASS |
|
|
Just needs landscaping.
|
ESC18-01748
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:33:54 AM | P | PASS |
|
|
No new activity. Front not landscaped.
|
ESC18-01441
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:33:16 AM | P | CANC |
|
|
|
ESC18-01441
| DOC - Permit Finaled | 2/28/2020 | 2/28/2020 | 2/28/2020 10:33:11 AM | P | PASS |
|
|
|
ESC17-01449
| Site Final | 2/28/2020 | 2/28/2020 | 2/28/2020 10:32:48 AM | P | PASS |
|
|
|
ESC19-01711
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:28:01 AM | P | PASS |
|
|
WIP on framing. Site is clean, no loose trash, wood scaps all piled next to trash box. Clean rock drive installed, no one parked in dirt.
|
ESC20-00248
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:21:21 AM | P | PASS |
|
|
Some site stripping, no new construction. Site is all contained.
|
ESC20-00115
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 10:15:05 AM | P | PASS |
|
|
Foundation has been poured, outpak washout on site. Natural buffer, nothing leaving site.
|
ESC19-01304
| Site Final | 2/28/2020 | 2/28/2020 | 2/28/2020 10:08:43 AM | P | PASS |
|
|
|
ESC19-00564
| Site Final | 2/28/2020 | 2/28/2020 | 2/28/2020 10:05:07 AM | P | PASS |
|
|
Demo done, wip on homes.
|
ESC18-01636
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 9:56:19 AM | | PASS |
|
|
Connection through to wise way not completed, no crew on site. Haul trucks not running material from ponds at time of inspection.
|
ESC17-00791
| General Inspection | 2/28/2020 | 2/28/2020 | 2/28/2020 9:38:04 AM | | PASS |
|
|
No activity.
|