ESC19-00083
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 1:40:44 PM | | PASS |
|
|
Still needs landscaping.
|
ESC19-00086
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 1:33:15 PM | | CANC |
|
|
|
ESC19-01584
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 12:22:04 PM | P | PASS |
|
|
Trenching for sewer taps is done. CXrew on site, looks like they are doing fill for seepage beds. No trackout.
|
ESC18-00497
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 12:13:50 PM | | PASS |
|
|
Will continue to monitor revegetation.
|
ESC19-01673
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 12:08:55 PM | P | PASS |
|
|
No access from cole, sidewalk and landscaping completed. Met with PM at site, parks dept also inspecting site. Currently getting final grade on pond, ditch has been tiled, doing pressure test. Some tracking out onto Glenwood, has sweeper twice a week.
|
ESC19-00401
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 11:36:33 AM | P | PART |
|
|
Met with owners rep at site. Area fenced off, looks like people are going through lots to still cut corner and avoid stop light. No dirt leaving site, roads within site are dirty. Work on 4 foundations, still setting forms, washout on site.
|
ESC20-00054
| Site Preparation | 3/6/2020 | 3/6/2020 | 3/6/2020 11:24:39 AM | P | DONE |
|
|
No one on site. Contaced RP to get prep inspection scheduled next week. Neighbor concerned ditch was covered and irragation starts soon, refered to Bob.
|
ESC20-00041
| Site Final | 3/6/2020 | 3/6/2020 | 3/6/2020 10:41:00 AM | P | PASS |
|
|
|
ESC18-00426
| Tracking Control | 3/4/2020 | 3/6/2020 | 3/6/2020 10:32:02 AM | A | PART |
|
|
Street looks like it was swept. Workers parked in area, looks like some new tracking coming from site. Should be cleaned when everyone off site.
|
ESC18-01674
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 10:19:41 AM | | CANC |
|
|
|
ESC18-01674
| DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 10:19:36 AM | P | PASS |
|
|
|
ESC19-00160
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 10:10:27 AM | P | FAIL |
|
|
phase 2 No foundation work has begun. Lots of loose trash on site and blown onto lot across street, cans, wrappers, etc. No construction entrance to site from road or existing apartments. Bunch of random trash and materials along fence on southern perimeter.
|
ESC18-01444
| General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 10:08:30 AM | | CANC |
|
|
|
ESC18-01444
| DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 10:08:25 AM | P | PASS |
|
|
All units done and landscaped. Will monitor site under phase 2 permit ESC19-00160
|
ESC19-01654
| General Inspection | 2/19/2020 | 3/6/2020 | 3/6/2020 9:48:01 AM | A | PASS |
|
|
WIp on elevation for building pad. Still ony grading permit, no building permit issued yet. Eldon is doing weekly inspections. Site is clean, will leave existing pavement in place for parking.
|
ESC19-00653
| Aging Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 9:06:15 AM | | CANC |
|
|
|
ESC19-00653
| DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 9:06:11 AM | P | PASS |
|
|
|