ESC17-00519
| General Inspection | 4/6/2018 | 4/11/2018 | 4/16/2018 11:40:38 AM | P | PEND |
|
|
Trackout onto Obelisks & Columbia. Sunroc is hauling into material for roadbed.
|
ESC17-00677
| General Inspection | 4/11/2018 | 4/11/2018 | 4/12/2018 11:52:02 AM | | PASS |
|
|
Home complete, needs landscaping.
|
ESC15-00556
| General Inspection | 4/11/2018 | 4/11/2018 | 4/12/2018 11:51:40 AM | | PART |
|
|
Taboo street needs to be cleaned and inlets maintained. Landscapers are storing gravel on road.
|
ESC17-00679
| General Inspection | 4/11/2018 | 4/11/2018 | 4/12/2018 11:46:51 AM | | PASS |
|
|
WIP on framing. Some lumber scraps laying around.
|
ESC17-00140
| General Inspection | 4/11/2018 | 4/11/2018 | 4/11/2018 3:10:31 PM | | PASS |
|
|
Exterior work mostly completed, still some work on back of home. Lot is contained, no runoff.
|
ESC17-00789
| Aging Inspection | 4/11/2018 | 4/11/2018 | 4/11/2018 2:58:44 PM | | PASS |
|
|
WIP. Disturbed area contained to backyard.
|
ESC16-00353
| General Inspection | 4/11/2018 | 4/11/2018 | 4/11/2018 2:42:41 PM | | PASS |
|
|
WIP on homesites. Lots are stabalized. Lots of sand is at bottom of hill.
|
ESC16-00617
| General Inspection | 4/11/2018 | 4/11/2018 | 4/11/2018 2:30:43 PM | | PASS |
|
|
WIP on framing. No issues at site.
|
ESC17-00781
| Aging Inspection | 4/11/2018 | 4/11/2018 | 4/11/2018 1:32:50 PM | | PASS |
|
|
Waiting on gates to close building permit. Unrelated to pool, hillside blow out that civil engineer is now working on.
|
ESC17-00190
| General Inspection | 4/11/2018 | 4/11/2018 | 4/11/2018 1:14:52 PM | | PART |
|
|
Some rills forming on hillsides, grass is also beginning to grow, will need to monitor stabalization vs erosion. Some sediment on drives of upper lots. Bare driveway access will need wattle or other BMP to slow down runoff and prevent more future rilling. Some rills starting to gorm into retention pond.
|
ESC17-00954
| General Inspection | 4/9/2018 | 4/11/2018 | 4/11/2018 1:04:54 PM | A | PASS |
|
|
Check BMP repairs. Cleaning out areas that were full of sediment. RPC is working on wall at top, when they finish new check dams will be built on road. Area on lower lot that blew out has been repaired. DI on bottom of hill has been replaced, still dirt in gutters going down hill.
|